Permitting Action Modification History
Modifications on 11/04/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-01-2026 | 08-11-2026 | 09-25-2026 | Yes |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | 07-01-2026 | 09-10-2026 | 10-23-2026 | Yes |
| ESA Consultation Concludes (Agency Action) | 11-13-2026 | 01-23-2027 | 11-03-2026 | Yes |
Modifications on 10/29/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-01-2026 | 08-11-2026 | 09-25-2026 | Yes |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | 07-01-2026 | 09-10-2026 | 10-23-2026 | Yes |
| ESA Consultation Concludes (Agency Action) | 11-13-2026 | 01-23-2027 | 11-23-2026 | No |
Modifications on 09/25/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-01-2026 | 08-11-2026 | 09-25-2026 | Yes |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-01-2026 | 09-10-2026 | 10-26-2026 | No |
| ESA Consultation Concludes (Agency Action) | 11-13-2026 | 01-23-2027 | 01-22-2027 | No |
Modifications on 08/28/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-01-2026 | 08-11-2026 | 09-25-2026 | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-01-2026 | 09-10-2026 | 10-26-2026 | No |
| ESA Consultation Concludes (Agency Action) | 11-13-2026 | 01-23-2027 | 01-22-2027 | No |
Modifications on 06/25/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-01-2026 | 08-11-2026 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-01-2026 | 09-10-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 11-13-2026 | 01-23-2027 | --- | No |
Modifications on 12/29/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-01-2026 | 06-01-2026 | --- | No |
| FWS determines ESA Consultation Package is Complete - Formal (Agency Action) | 07-01-2026 | 07-01-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 11-13-2026 | 11-13-2026 | --- | No |
Modifications on 12/29/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-01-2026 | 06-01-2026 | --- | No |
| FWS determines ESA Consultation Package is Complete - Informal (Agency Action) | 07-01-2026 | 07-01-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 11-13-2026 | 11-13-2026 | --- | No |
Modifications on 12/19/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| ESA Consultation Request Package Submitted (Agency Action) | 06-01-2026 | 06-01-2026 | --- | No |
| ESA Consultation Concludes (Agency Action) | 11-13-2026 | 11-13-2026 | --- | No |