Black Bear Natural Gas Development

PERMITTING DASHBOARD PROJECT POSTING DATE: OCTOBER 28, 2025

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/11/2027

0 out of 5

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production

SECTOR
Conventional Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Description:

The Black Bear Natural Gas Development Project includes the construction and operation of three natural gas well pads—Bear Creek, High Plains, and Wolf Creek—located across private land, the Angelina and Sabine National Forests, and USACE surface areas in San Augustine and Sabine Counties, Texas. Each pad will host up to eight horizontally drilled wells targeting private and USFS‑managed minerals.

The project also includes a 36‑inch main gathering pipeline approximately 32 miles long and three secondary 30‑inch gathering lines connecting each pad to the main line. Pipeline construction will use trenching and horizontal directional drilling at streams, wetlands, roads, and other sensitive areas. Temporary access roads, pad‑specific lease roads, and a lay‑flat waterline supplying drilling water from Sam Rayburn Reservoir are also part of the project.

The Executive Director granted a Bureau of Land Management request to extend completion dates for all actions on June 25, 2026.  The Executive Director Determination is posted here.

Permitting Timetable

The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.

  • For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
Loading ...
Overall Project Timetable
 
STATUS
Schedule
Extension or Delay
Ahead of Schedule
Paused
No End Date
Planned

Action Information

For additional information, please select an Action from the Permitting Timetable above.

  • Action:  
  • Responsible Agency:  
  • Bureau:  
  • Action Status:  
  • SHPO:  
  • Action Identifier:  
  • Action Outcome:  
Milestone Original Target Date Current Target Date Milestone Complete