Coastal Virginia Offshore Wind Commercial Project
PERMITTING DASHBOARD PROJECT POSTING DATE: FEBRUARY 12, 2021PROJECT WEBSITE: Coastal Virginia Offshore Wind
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
							ENVIRONMENTAL REVIEW AND PERMITTING STATUS
							COMPLETE
						
																					COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
																																04/09/2024
																					
							ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
							COMPLETED
						
								SECTOR
								Renewable Energy Production
							
							CATEGORY
																						
								Project Category
              FAST-41 Covered Projects
																				
								LEAD AGENCY
																	Department of the Interior, Bureau of Ocean Energy Management
															
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Department of Commerce, National Oceanic and Atmospheric Administration
Environmental Protection Agency
Description:
Dominion Energy is proposing to construct, own, and operate the Coastal Virginia Offshore Wind (CVOW) Commercial Project (the Project). The Project will be located in the Commercial Lease of Submerged Lands for Renewable Energy Development on the Outer Continental Shelf Offshore Virginia (Lease No. OCS-A-0483) (Lease Area). The Lease Area, located within Official Protraction Diagram NJ18-11 Currituck Sound, covers approximately 112,799 acres (45,658 hectares) and is approximately 27 statute miles (23.75 nautical miles, 43.99 kilometers) off the Virginia Beach coastline.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the NEPA, COP, Section 106, Sections 10/404/408, Real Estate Authorization and Certification, and OCS air permit actions on March 30, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the OCS air permit action on Jan 05 2024. The Executive Director determination is posted here.
To view timetable chart, please turn device sideways (landscape)
Permitting Timetable
The permitting timetable below displays data as reported by agencies. Dates for Environmental Review and Permitting processes (Actions) that are in 'Paused' or 'Planned' status are subject to change and are not indicative of a project's final schedule.
- For information about extensions, select an Action from the timetable below and select 'View Action Details' at the bottom of the page.
 
Action Information
For additional information, please select an Action from the Permitting Timetable above.
- Action:
 - Responsible Agency:
 - Bureau:
 - Action Status:
 - SHPO:
 - Action Identifier:
 - Action Outcome:
 
| Milestone | Original Target Date | Current Target Date | Milestone Complete | 
|---|