USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
The milestone was completed earlier than anticipated. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 07-03-2022 07-01-2022 --- Yes
Completed application received (Applicant Action) 08-03-2022 09-15-2022 --- Yes
Issuance of decision for permit/approval (Agency Action 08-31-2023 04-26-2023 --- Yes
In Progress
Notified by BOEM that ROD dates has changed and Executive Director approval is required. Updated USACE decision dates based on BOEM's changes to ROD date. USACE decision date remains at 90 days post-ROD. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 07-03-2022 07-01-2022 --- Yes
Completed application received (Applicant Action) 08-03-2022 09-15-2022 --- Yes
Issuance of decision for permit/approval (Agency Action 08-31-2023 01-29-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 07-03-2022 07-01-2022 --- Yes
Completed application received (Applicant Action) 08-03-2022 09-15-2022 --- Yes
Issuance of decision for permit/approval (Agency Action 08-31-2023 08-31-2023 --- No
In Progress
Complete application can't be submitted until the Project Sponsor receives SSC approval, anticipated in August 2022.  Project sponsor requested that "Completed Application Received" milestone be moved to 10/1/22.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 07-01-2022 07-01-2022 --- Yes
Completed application received (Applicant Action) 10-01-2022 10-01-2022 --- No
Issuance of decision for permit/approval (Agency Action 08-31-2023 08-31-2023 --- No