Agency Milestone Date of 04/30/2026 for Final decision/agency action (Agency Action) has passed by 1 business days
Cooperating under NEPA
Milestones:
-
Non-conformance Explanation:The Bureau of Reclamation (Reclamation) missed the April 30, 2026, milestone to complete the use authorization. Per 42 U.S.C.§ 4370m-2(c)(2)(F), Reclamation is required to provide an alternative completion date and an initial explanation for the missed completion date by May 11, 2026. Reclamation has provided the initial explanation for the missed date but has not yet provided the required alternative completion date. The Permitting Council is working with Reclamation to ensure an alternative completion date is determined and represented on the permitting timetable as soon as possible. Modifications to the language of the use authorization agreement were requested at the end of April delayed the execution of the agreement and prompted additional internal reviews.
Additional Milestones:
-
Non-conformance Explanation:The Bureau of Reclamation (Reclamation) missed the April 30, 2026, milestone to complete the use authorization. Per 42 U.S.C.§ 4370m-2(c)(2)(F), Reclamation is required to provide an alternative completion date and an initial explanation for the missed completion date by May 11, 2026. Reclamation has provided the initial explanation for the missed date but has not yet provided the required alternative completion date. The Permitting Council is working with Reclamation to ensure an alternative completion date is determined and represented on the permitting timetable as soon as possible. Modifications to the language of the use authorization agreement were requested at the end of April delayed the execution of the agreement and prompted additional internal reviews.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/20/2026
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Broadband
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Interior, Bureau of Reclamation
Department of the Interior, Bureau of Land Management
Description:
The Navajo Nation Department of Education proposes to deploy a reliable, affordable, scalable,
and future-proofed broadband network that bridges the digital divide for the foreseeable future in some of the most remote, isolated, high-cost, and difficult to serve areas of the United States. The Navajo Nation Department of Education E-Rate Funded Broadband Project consists of constructing approximately 323 miles of middle mile fiber optic network on the Navajo Nation to connect 17 Head Start entities and 33 libraries with high-speed Internet connectivity to speeds of 1 Gbps or greater.
The Executive Director granted a Bureau of Indian Affairs request to extend the NEPA; Section 106; Right-of-Way (BLM); Right-of-Way (BIA); Use Authorization (BOR); and Endangered Species Act (FWS) completion dates on March 31, 2025. The Executive Director determination is posted here.
The project proponent is developing the project in phases. Phase I would provide internet service from Ya’ta’hey to San Juan Chapter, New Mexico, as considered in the Ya’ta’hey to San Juan Chapter, New Mexico Fiber Optic Broadband Cable Navajo Nation Division of Education Environmental Assessment (EA-26-012726). Phase II of the proposed project would serve the 11 Navajo communities; starting with San Juan Chapter, Bloomfield to Counselor and Huerfano, Crownpoint, Lake Valley, White Rock, Becenti, Rock Springs, Bread Springs, Casamero Lake, Churchrock, Pinedale, Mariano Lake, and Pueblo Pintado.
-
Non-conformance Explanation:The Bureau of Reclamation (Reclamation) missed the April 30, 2026, milestone to complete the use authorization. Per 42 U.S.C.§ 4370m-2(c)(2)(F), Reclamation is required to provide an alternative completion date and an initial explanation for the missed completion date by May 11, 2026. Reclamation has provided the initial explanation for the missed date but has not yet provided the required alternative completion date. The Permitting Council is working with Reclamation to ensure an alternative completion date is determined and represented on the permitting timetable as soon as possible. Modifications to the language of the use authorization agreement were requested at the end of April delayed the execution of the agreement and prompted additional internal reviews.