Permitting Action Modification History
Modifications on 10/26/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-05-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 11-17-2025 | 03-17-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-23-2025 | 04-30-2026 | 10-23-2026 | Yes |
Modifications on 10/01/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-05-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 11-17-2025 | 03-17-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-23-2025 | 04-30-2026 | 10-30-2026 | No |
Modifications on 09/11/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-05-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 11-17-2025 | 03-17-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-23-2025 | 04-30-2026 | 09-18-2026 | No |
Modifications on 07/10/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-05-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 11-17-2025 | 03-17-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-23-2025 | 04-30-2026 | 08-31-2026 | No |
Modifications on 06/15/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-05-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 11-17-2025 | 03-17-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-23-2025 | 04-30-2026 | 06-26-2026 | No |
Modifications on 06/03/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-05-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 11-17-2025 | 03-17-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-23-2025 | 04-30-2026 | 06-12-2026 | No |
Modifications on 03/17/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-05-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 11-17-2025 | 03-17-2026 | --- | Yes |
| Final decision/agency action (Agency Action) | 12-23-2025 | 04-30-2026 | --- | No |
Modifications on 04/01/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-05-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 11-17-2025 | 03-17-2026 | --- | No |
| Final decision/agency action (Agency Action) | 12-23-2025 | 04-30-2026 | --- | No |
Modifications on 02/10/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-05-2025 | --- | Yes |
| Application deemed complete (Agency Action) | 11-17-2025 | 11-17-2025 | --- | No |
| Final decision/agency action (Agency Action) | 12-23-2025 | 12-23-2025 | --- | No |
Modifications on 02/03/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 02-14-2025 | --- | No |
| Application deemed complete (Agency Action) | 11-17-2025 | 11-17-2025 | --- | No |
| Final decision/agency action (Agency Action) | 12-23-2025 | 12-23-2025 | --- | No |
Modifications on 01/07/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application submitted (Applicant Action) | 01-31-2025 | 01-31-2025 | --- | No |
| Application deemed complete (Agency Action) | 11-17-2025 | 11-17-2025 | --- | No |
| Final decision/agency action (Agency Action) | 12-23-2025 | 12-23-2025 | --- | No |