USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
The applicant has requested additional time to address Coast Guard comments regarding the initial application. Following the applicant's submission of the requested information, the Coast Guard will undertake a final review to ascertain completeness. The current milestone for Application Deemed Complete is identified as August 18, 2025.  The applicant and the Coast Guard have agreed to revise this date to September 8, 2025. This schedule adjustment is not anticipated to impact the projected date of final permit issuance.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Navigation Data Submitted (Applicant Action) 05-16-2025 05-16-2025 --- Yes
Issued Preliminary Navigation Clearance Determination (Agency Action) 05-16-2025 05-16-2025 --- Yes
Initial Application Submitted (Applicant Action) 05-16-2025 06-16-2025 --- Yes
Publication of Public Notice (Agency Action) 06-16-2025 07-14-2025 --- Yes
Application Deemed Complete (Agency Action) 11-07-2025 09-08-2025 --- No
Permit Decision Rendered (Agency Action) 02-05-2026 11-17-2025 --- No
Planned
Milestone completed 3 days earlier than scheduled.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Navigation Data Submitted (Applicant Action) 05-16-2025 05-16-2025 --- Yes
Issued Preliminary Navigation Clearance Determination (Agency Action) 05-16-2025 05-16-2025 --- Yes
Initial Application Submitted (Applicant Action) 05-16-2025 06-16-2025 --- Yes
Publication of Public Notice (Agency Action) 06-16-2025 07-14-2025 --- Yes
Application Deemed Complete (Agency Action) 11-07-2025 08-18-2025 --- No
Permit Decision Rendered (Agency Action) 02-05-2026 11-17-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Navigation Data Submitted (Applicant Action) 05-16-2025 05-16-2025 --- Yes
Issued Preliminary Navigation Clearance Determination (Agency Action) 05-16-2025 05-16-2025 --- Yes
Initial Application Submitted (Applicant Action) 05-16-2025 06-16-2025 --- Yes
Publication of Public Notice (Agency Action) 06-16-2025 07-17-2025 --- No
Application Deemed Complete (Agency Action) 11-07-2025 08-18-2025 --- No
Permit Decision Rendered (Agency Action) 02-05-2026 11-17-2025 --- No
Planned
Due to the elimination of certain outside agency reviews, the Coast Guard's application completeness determination can be expedited. Consequently, the Permit Decision Rendered date is also anticipated to be accelerated.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Navigation Data Submitted (Applicant Action) 05-16-2025 05-16-2025 --- Yes
Issued Preliminary Navigation Clearance Determination (Agency Action) 05-16-2025 05-16-2025 --- Yes
Initial Application Submitted (Applicant Action) 05-16-2025 06-17-2025 --- No
Publication of Public Notice (Agency Action) 06-16-2025 07-17-2025 --- No
Application Deemed Complete (Agency Action) 11-07-2025 08-18-2025 --- No
Permit Decision Rendered (Agency Action) 02-05-2026 11-17-2025 --- No
Planned
The applicant did not submit the application as scheduled.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Navigation Data Submitted (Applicant Action) 05-16-2025 05-16-2025 --- Yes
Issued Preliminary Navigation Clearance Determination (Agency Action) 05-16-2025 05-16-2025 --- Yes
Initial Application Submitted (Applicant Action) 05-16-2025 06-17-2025 --- No
Publication of Public Notice (Agency Action) 06-16-2025 07-17-2025 --- No
Application Deemed Complete (Agency Action) 11-07-2025 11-07-2025 --- No
Permit Decision Rendered (Agency Action) 02-05-2026 02-05-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Navigation Data Submitted (Applicant Action) 05-16-2025 05-16-2025 --- Yes
Issued Preliminary Navigation Clearance Determination (Agency Action) 05-16-2025 05-16-2025 --- Yes
Initial Application Submitted (Applicant Action) 05-16-2025 05-16-2025 --- No
Publication of Public Notice (Agency Action) 06-16-2025 06-16-2025 --- No
Application Deemed Complete (Agency Action) 11-07-2025 11-07-2025 --- No
Permit Decision Rendered (Agency Action) 02-05-2026 02-05-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Navigation Data Submitted (Applicant Action) 05-16-2025 05-16-2025 --- No
Issued Preliminary Navigation Clearance Determination (Agency Action) 05-16-2025 05-16-2025 --- No
Initial Application Submitted (Applicant Action) 05-16-2025 05-16-2025 --- No
Publication of Public Notice (Agency Action) 06-16-2025 06-16-2025 --- No
Application Deemed Complete (Agency Action) 11-07-2025 11-07-2025 --- No
Permit Decision Rendered (Agency Action) 02-05-2026 02-05-2026 --- No