Agency Milestone Date of 09/22/2023 for Section 106 consultation concluded (Agency Action) has passed by 1 business days
Milestones:
-
Monthly Status Report for November 2024:On track to meet the final milestone. The MOA is circulating for execution.
-
Monthly Status Report for October 2024:On track to meet the final milestone. The MOA has been drafted and is anticipated to circulate for signature shortly, after completing internal review.
-
Monthly Status Report for September 2024:BOEM is on track to meet the final milestone. The fifth consulting party meeting is scheduled for Oct 8.
-
Monthly Status Report for August 2024:BOEM is scheduling the fifth consulting party meeting in October and is on track to meet the December milestone.
-
Monthly Status Report for July 2024:BOEM is scheduling the fifth consulting party meeting in Sep and is on track to meet the December milestone.
-
Monthly Status Report for June 2024:BOEM is scheduling the fourth consulting party meeting in July and is on track to meet the December milestone.
-
Monthly Status Report for May 2024:BOEM is scheduling the fourth consulting party meeting in July and is on track to meet the December milestone.
-
Monthly Status Report for April 2024:BOEM is planning on holding the fourth consulting party meeting in June and is on track to meet the milestone date.
-
Monthly Status Report for March 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in 3 convening meetings with the Permitting Council and the Sponsor. BOEM is currently undertaking a final review of the revised permitting timetable to reset the schedule for the remaining milestones.
-
Monthly Status Report for February 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in three convening meetings with the Permitting Council and the Sponsor and currently has a revised permitting timetable before the Permitting Council to reset the schedule for the remaining milestones.
-
Monthly Status Report for January 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompassed all agency actions and milestone dates for the project, including this action. Based on that review, in December of 2023, BOEM developed a revised permitting timetable. The Permitting Council has scheduled a convening meeting in February of 2024 to further consult on the proposed timetable.
-
Monthly Status Report for December 2023:BOEM is undertaking a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompasses all agency actions and milestone dates for the project, including this action. The review will result in an updated permitting time table for all actions, including this milestone.
-
Monthly Status Report for November 2023:Pending the Sponsor's submittal to NMFS of supplemental information for their MMPA application, BOEM will undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action. Upon completing that review, BOEM will submit to FPISC a request for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action.
-
Monthly Status Report for October 2023:Pending the Sponsor's submittal to NMFS of supplemental information for their MMPA application, BOEM will undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action. Upon completing that review, BOEM will submit to FPISC a request for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action.
-
Non-conformance Explanation:Pending the resolution of outstanding concerns with the MMPA action, BOEM plans to undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action.
-
Monthly Status Report for November 2024:On track to meet the final milestone. The MOA is circulating for execution.
-
Monthly Status Report for October 2024:On track to meet the final milestone. The MOA has been drafted and is anticipated to circulate for signature shortly, after completing internal review.
-
Monthly Status Report for September 2024:BOEM is on track to meet the final milestone. The fifth consulting party meeting is scheduled for Oct 8.
-
Monthly Status Report for August 2024:BOEM is scheduling the fifth consulting party meeting in October and is on track to meet the December milestone.
-
Monthly Status Report for July 2024:BOEM is scheduling the fifth consulting party meeting in Sep and is on track to meet the December milestone.
-
Monthly Status Report for June 2024:BOEM is scheduling the fourth consulting party meeting in July and is on track to meet the December milestone.
-
Monthly Status Report for May 2024:BOEM is scheduling the fourth consulting party meeting in July and is on track to meet the December milestone.
-
Monthly Status Report for April 2024:BOEM is planning on holding the fourth consulting party meeting in June and is on track to meet the milestone date.
-
Monthly Status Report for March 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in 3 convening meetings with the Permitting Council and the Sponsor. BOEM is currently undertaking a final review of the revised permitting timetable to reset the schedule for the remaining milestones.
-
Monthly Status Report for February 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in three convening meetings with the Permitting Council and the Sponsor and currently has a revised permitting timetable before the Permitting Council to reset the schedule for the remaining milestones.
-
Monthly Status Report for January 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompassed all agency actions and milestone dates for the project, including this action. Based on that review, in December of 2023, BOEM developed a revised permitting timetable. The Permitting Council has scheduled a convening meeting in February of 2024 to further consult on the proposed timetable.
-
Monthly Status Report for December 2023:BOEM is undertaking a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompasses all agency actions and milestone dates for the project, including this action. The review will result in an updated permitting time table for all actions, including this milestone.
-
Monthly Status Report for November 2023:Pending the Sponsor's submittal to NMFS of supplemental information for their MMPA application, BOEM will undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action. Upon completing that review, BOEM will submit to FPISC a request for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action.
-
Monthly Status Report for October 2023:Pending the Sponsor's submittal to NMFS of supplemental information for their MMPA application, BOEM will undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action. Upon completing that review, BOEM will submit to FPISC a request for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action.
-
Non-conformance Explanation:Pending the resolution of outstanding concerns with the MMPA action, BOEM plans to undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action.
PROJECT WEBSITE: https://southcoastwind.com/
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
06/26/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Description:
Updated February 2023: Mayflower Wind Project name changed to SouthCoast Wind Project.
The purpose of the SouthCoast Wind Project is to provide clean, renewable wind energy to the Northeast United States, including to Massachusetts. SouthCoast Wind will support reliability in Massachusetts and in the New England region, while meeting the Commonwealth’s statutory need for renewable/clean energy. The SouthCoast Wind Project also supports the federal need of grid reliability, as set forth the Federal Power Act in Section 215. Out of the 6.7 million people living in Massachusetts, nearly 5.1 million people live along coastal areas of the state. Offshore wind projects like SouthCoast Wind can provide a localized energy source to coastal populations.
The Environmental Review and Permitting Status of this project will be changed to "In Progress" once the Notice of Intent to prepare an Environmental Impact Statement (EIS) has been issued.
-
Monthly Status Report for November 2024:On track to meet the final milestone. The MOA is circulating for execution.
-
Monthly Status Report for October 2024:On track to meet the final milestone. The MOA has been drafted and is anticipated to circulate for signature shortly, after completing internal review.
-
Monthly Status Report for September 2024:BOEM is on track to meet the final milestone. The fifth consulting party meeting is scheduled for Oct 8.
-
Monthly Status Report for August 2024:BOEM is scheduling the fifth consulting party meeting in October and is on track to meet the December milestone.
-
Monthly Status Report for July 2024:BOEM is scheduling the fifth consulting party meeting in Sep and is on track to meet the December milestone.
-
Monthly Status Report for June 2024:BOEM is scheduling the fourth consulting party meeting in July and is on track to meet the December milestone.
-
Monthly Status Report for May 2024:BOEM is scheduling the fourth consulting party meeting in July and is on track to meet the December milestone.
-
Monthly Status Report for April 2024:BOEM is planning on holding the fourth consulting party meeting in June and is on track to meet the milestone date.
-
Monthly Status Report for March 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in 3 convening meetings with the Permitting Council and the Sponsor. BOEM is currently undertaking a final review of the revised permitting timetable to reset the schedule for the remaining milestones.
-
Monthly Status Report for February 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the Sponsor. The review encompassed all remaining milestone dates for the project, including this one. Based on that review, in December of 2023, BOEM initiated development of a revised permitting timetable. BOEM subsequently participated in three convening meetings with the Permitting Council and the Sponsor and currently has a revised permitting timetable before the Permitting Council to reset the schedule for the remaining milestones.
-
Monthly Status Report for January 2024:BOEM undertook a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompassed all agency actions and milestone dates for the project, including this action. Based on that review, in December of 2023, BOEM developed a revised permitting timetable. The Permitting Council has scheduled a convening meeting in February of 2024 to further consult on the proposed timetable.
-
Monthly Status Report for December 2023:BOEM is undertaking a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompasses all agency actions and milestone dates for the project, including this action. The review will result in an updated permitting time table for all actions, including this milestone.
-
Monthly Status Report for November 2023:Pending the Sponsor's submittal to NMFS of supplemental information for their MMPA application, BOEM will undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action. Upon completing that review, BOEM will submit to FPISC a request for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action.
-
Monthly Status Report for October 2023:Pending the Sponsor's submittal to NMFS of supplemental information for their MMPA application, BOEM will undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action. Upon completing that review, BOEM will submit to FPISC a request for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action.
-
Non-conformance Explanation:Pending the resolution of outstanding concerns with the MMPA action, BOEM plans to undertake a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review will encompass all NEPA and associated agency actions and milestone dates for the project, including this action.