Permitting Action Modification History

Complete
MOA was executed 1 day early, on December 18, 2024 , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 11-01-2021 11-01-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 09-29-2021 09-29-2021 --- Yes
Section 106 consultation concluded (Agency Action) 09-22-2023 09-22-2023 12-18-2024 Yes
In Progress
Section 106 consultation is being conducted through the Section 106 NEPA substitution process and therefore, the final Section 106 milestone is shifting in accordance with the ROD milestone shift. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 11-01-2021 11-01-2021 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 09-29-2021 09-29-2021 --- Yes
Section 106 consultation concluded (Agency Action) 09-22-2023 09-22-2023 12-19-2024 No