Agency Milestone Date of 11/24/2023 for Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) has passed by 1 business days
Milestones:
-
Monthly Status Report for March 2024:BOEM met the FEIS milestone of March 1 and is on track to publish the ROD on April 1.
-
Monthly Status Report for February 2024:BOEM will meet the March 1, 2024 milestone to publish the NOA in the Federal Register. For the subsequent milestone, BOEM is currently coordinating with cooperating agencies to finalize the Record of Decision and is on track to meet the ROD milestone of April 1, 2024.
-
Monthly Status Report for January 2024:BOEM anticipates publishing the NOA for the FEIS on March 1, 2024. This aligns with the updated permitting timetable provided to the Permitting Council as part of an Executive Director Determination (EDD) request in December of 2023. While this milestone did not need an EDD to be updated, it was included in the revised permitting timetable in the EDD request. BOEM received the EDD on Jan 12, 2024.
-
Non-conformance Explanation:BOEM completed a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompassed all agency actions and milestone dates for the project, including this action. BOEM provided the Permitting Council with an updated permitting timetable on Dec 15, 2023 for all actions, including this milestone.
Additional Milestones:
BOEM is undertaking additional scoping for two new variations of the offshore export cable corridor submitted by the project sponsor. The submission was received after the initial scoping period ended.
Federal Register Notice link: https://www.federalregister.gov/documents/2021/11/22/2021-25320/notice-of-additional-public-scoping-and-name-change-for-the-vineyard-wind-south-project-offshore.
-
Monthly Status Report for March 2024:BOEM met the FEIS milestone of March 1 and is on track to publish the ROD on April 1.
-
Monthly Status Report for February 2024:BOEM will meet the March 1, 2024 milestone to publish the NOA in the Federal Register. For the subsequent milestone, BOEM is currently coordinating with cooperating agencies to finalize the Record of Decision and is on track to meet the ROD milestone of April 1, 2024.
-
Monthly Status Report for January 2024:BOEM anticipates publishing the NOA for the FEIS on March 1, 2024. This aligns with the updated permitting timetable provided to the Permitting Council as part of an Executive Director Determination (EDD) request in December of 2023. While this milestone did not need an EDD to be updated, it was included in the revised permitting timetable in the EDD request. BOEM received the EDD on Jan 12, 2024.
-
Non-conformance Explanation:BOEM completed a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompassed all agency actions and milestone dates for the project, including this action. BOEM provided the Permitting Council with an updated permitting timetable on Dec 15, 2023 for all actions, including this milestone.
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/22/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Renewable Energy Production
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of Commerce, National Oceanic and Atmospheric Administration
Department of the Army, US Army Corps of Engineers - Regulatory
Department of the Interior, Fish and Wildlife Service
Environmental Protection Agency
Description:
Update: In October 2021, the project name changed from Vineyard Wind South to New England Wind to reflect restructuring of the project’s parent companies (for more information, see Vineyard Wind’s September 21, 2021 press release).
New England Wind is the proposal to develop offshore renewable wind energy facilities in BOEM Lease Area OCS-A 0534 along with associated offshore and onshore cabling, onshore substations, and onshore operations and maintenance (O&M) facilities. Park City Wind LLC, a wholly owned subsidiary of Avangrid Renewables, LLC, is the Proponent and would be responsible for the construction, operation, and decommissioning of New England Wind. New England Wind will be developed in two Phases. If approved, Phase 1, also known as the Park City Wind project, will be developed in the northeastern portion of Lease Area OCS-A 0534. Phase 2, also known as Commonwealth Wind, will be located southwest of Phase 1.
FAST-41 provides increased transparency and predictability by requiring Federal agencies to publish comprehensive permitting timetables for all "covered" projects, and provides clear procedures for modifying permitting timetables to address the unpredictability inherent in the environmental review and permitting process for significant infrastructure projects. For more information, see "The FAST-41 Process" at https://www.permits.performance.gov/fpisc-content/fast-41-process.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the NEPA, COP, Section 106, Sections 10/404, and OCS air permit actions completion date on May 10, 2023. The Executive Director determination is posted here.
The Executive Director granted a Bureau of Ocean Energy Management (BOEM) request to extend the Section 106 actions completion date on Nov 22, 2023. The Executive Director determination is posted here.
</p>
-
Monthly Status Report for March 2024:BOEM met the FEIS milestone of March 1 and is on track to publish the ROD on April 1.
-
Monthly Status Report for February 2024:BOEM will meet the March 1, 2024 milestone to publish the NOA in the Federal Register. For the subsequent milestone, BOEM is currently coordinating with cooperating agencies to finalize the Record of Decision and is on track to meet the ROD milestone of April 1, 2024.
-
Monthly Status Report for January 2024:BOEM anticipates publishing the NOA for the FEIS on March 1, 2024. This aligns with the updated permitting timetable provided to the Permitting Council as part of an Executive Director Determination (EDD) request in December of 2023. While this milestone did not need an EDD to be updated, it was included in the revised permitting timetable in the EDD request. BOEM received the EDD on Jan 12, 2024.
-
Non-conformance Explanation:BOEM completed a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompassed all agency actions and milestone dates for the project, including this action. BOEM provided the Permitting Council with an updated permitting timetable on Dec 15, 2023 for all actions, including this milestone.