Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2021 06-30-2021 --- Yes
Scoping (Agency Action) 07-30-2021 07-30-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-26-2022 12-23-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-23-2023 11-24-2023 03-01-2024 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 07-23-2023 12-26-2023 04-01-2024 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2021 06-30-2021 --- Yes
Scoping (Agency Action) 07-30-2021 07-30-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-26-2022 12-23-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-23-2023 11-24-2023 03-01-2024 Yes
Issuance of Lead Agency Record of Decision (Agency Action) 07-23-2023 12-26-2023 04-01-2024 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2021 06-30-2021 --- Yes
Scoping (Agency Action) 07-30-2021 07-30-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-26-2022 12-23-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-23-2023 11-24-2023 03-01-2024 No
Issuance of Lead Agency Record of Decision (Agency Action) 07-23-2023 12-26-2023 04-01-2024 No
In Progress
BOEM requests an extension of completion dates for its NEPA action based on the following: (1) the Project Sponsor made an early design change that required re-scoping; (2) alternatives discussions between the lead and cooperating agencies; and (3) delays related to ESA and EFH consultations, which is relevant because BOEM includes information from those consultations in the final EIS. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2021 06-30-2021 --- Yes
Scoping (Agency Action) 07-30-2021 07-30-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-26-2022 12-23-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-23-2023 11-24-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-23-2023 12-26-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2021 06-30-2021 --- Yes
Scoping (Agency Action) 07-30-2021 07-30-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-26-2022 12-23-2022 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-23-2023 09-22-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-23-2023 07-23-2023 --- No
In Progress
The delay in BOEM receiving the draft EIS from its third-party contractor has in turn resulted in a corresponding delay for publication of the Draft and Final EISs and ROD. Reasons for the third-party contractor’s delay in delivering the draft EIS to BOEM include delays in the National Environmental Policy Act process resulting from an extended alternatives development period, as well as project modifications and additional information filed by the project sponsor.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2021 06-30-2021 --- Yes
Scoping (Agency Action) 07-30-2021 07-30-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-26-2022 12-23-2022 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-23-2023 09-22-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-23-2023 07-23-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2021 06-30-2021 --- Yes
Scoping (Agency Action) 07-30-2021 07-30-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-26-2022 11-10-2022 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-23-2023 06-23-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-23-2023 07-23-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 06-30-2021 06-30-2021 --- Yes
Scoping (Agency Action) 07-30-2021 07-30-2021 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 08-26-2022 08-26-2022 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 06-23-2023 06-23-2023 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 07-23-2023 07-23-2023 --- No