USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Environmental Impact Statement (EIS): Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 08/12/2026 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
Planned
POC Name:
Daltrey Balmer
POC Title:
Assistant Field Manager
POC Email:

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Current Target Date:
Scoping (Agency Action)
Current Target Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date:
Milestone
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Tonopah Flats Lithium Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/09/2027

0 out of 3

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Mining

SECTOR
Mining

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Description:

American Battery Technology Company (ABTC), an integrated critical battery materials company is proposing to construct and operate its Tonopah Flats Lithium Project (TFLP or Project). The Project boundary encompasses one discrete claim block totaling 10,340 acres of public lands administered by the BLM Battle Mountain District Tonopah Field Office, held through 517 lode claims.

ABTC proposes to conduct surface pit mining for lithium using benching, and truck and shovel methods. The deposit will be mined by conventional truck and shovel. The deposit does not intersect groundwater and is covered by about 50 feet of overburden. ABTC will continue exploration drilling throughout the Project in areas of the claim block not previously explored. Project duration is estimated at over 40 years. Total proposed disturbance including the proposed mine and supporting solar facility includes up to 8,842 acres of disturbance.

ABTC plans to construct and operate the surface pit mine and scalable processing facility. The Project facilities and surface disturbance will consist of one (1) pit, one (1) 37,700 ton-per-day milling and processing facility for lithium recovery and tailings dewatering, exploration drill pads, a behind-the-meter 4,439-acre solar photovoltaic field with associated battery energy storage systems, a new substation and power lines, access and haul roads, monitoring and supply wells, stormwater and sediment control, one (1) dry stack tailings facility, one (1) growth medium stockpile, and surface piping and conveyance. The processing facilities will generate a lithium hydroxide monohydrate (LiOH-H2O(s)) product for market.

 

field_status
System Comments
Agency Milestone Date of 08/12/2026 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
Approver Comments
<div class="x_elementToProof" style="-webkit-text-stroke-width:0px;background-color:white;border-width:0px;color:rgb(200, 38, 19);font-family:Aptos, Aptos_EmbeddedFont, Aptos_MSFontService, Calibri, Helvetica, sans-serif;font-feature-settings:inherit;font-kerning:inherit;font-language-override:inherit;font-optical-sizing:inherit;font-size-adjust:inherit;font-size:16px;font-stretch:inherit;font-style:normal;font-variant-alternates:inherit;font-variant-caps:normal;font-variant-east-asian:inherit;font-variant-emoji:inherit;font-variant-ligatures:normal;font-variant-numeric:inherit;font-variant-position:inherit;font-variation-settings:inherit;font-weight:400;letter-spacing:normal;line-height:inherit;margin:0px;orphans:2;padding:0px;text-align:left;text-decoration-color:initial;text-decoration-style:initial;text-decoration-thickness:initial;text-indent:0px;text-transform:none;vertical-align:baseline;white-space:normal;widows:2;word-spacing:0px;"><em><i data-olk-copy-source="MessageBody">The Bureau of Land Management (BLM) missed the August 12, 2026, milestone to publish the Notice of Intent to prepare an Environmental Impact Statement (EIS). The Notice of Intent for the Tonopah Flats Lithium Project has required enhanced coordination and administrative review and will be published once this is completed.</i></em></div><div class="x_elementToProof" style="-webkit-text-stroke-width:0px;background-color:white;border-width:0px;color:rgb(200, 38, 19);font-family:Aptos, Aptos_EmbeddedFont, Aptos_MSFontService, Calibri, Helvetica, sans-serif;font-feature-settings:inherit;font-kerning:inherit;font-language-override:inherit;font-optical-sizing:inherit;font-size-adjust:inherit;font-size:16px;font-stretch:inherit;font-style:normal;font-variant-alternates:inherit;font-variant-caps:normal;font-variant-east-asian:inherit;font-variant-emoji:inherit;font-variant-ligatures:normal;font-variant-numeric:inherit;font-variant-position:inherit;font-variation-settings:inherit;font-weight:400;letter-spacing:normal;line-height:inherit;margin:0px;orphans:2;padding:0px;text-align:left;text-decoration-color:initial;text-decoration-style:initial;text-decoration-thickness:initial;text-indent:0px;text-transform:none;vertical-align:baseline;white-space:normal;widows:2;word-spacing:0px;">&nbsp;</div><div class="x_elementToProof" style="-webkit-text-stroke-width:0px;background-color:white;border-width:0px;color:rgb(36, 36, 36);font-family:Aptos, Aptos_EmbeddedFont, Aptos_MSFontService, Calibri, Helvetica, sans-serif;font-feature-settings:inherit;font-kerning:inherit;font-language-override:inherit;font-optical-sizing:inherit;font-size-adjust:inherit;font-size:16px;font-stretch:inherit;font-style:normal;font-variant-alternates:inherit;font-variant-caps:normal;font-variant-east-asian:inherit;font-variant-emoji:inherit;font-variant-ligatures:normal;font-variant-numeric:inherit;font-variant-position:inherit;font-variation-settings:inherit;font-weight:400;letter-spacing:normal;line-height:inherit;margin:0px;orphans:2;padding:0px;text-align:left;text-decoration-color:initial;text-decoration-style:initial;text-decoration-thickness:initial;text-indent:0px;text-transform:none;vertical-align:baseline;white-space:normal;widows:2;word-spacing:0px;"><em><span style="border-width:0px;color:rgb(200, 38, 19);font:inherit;margin:0px;padding:0px;vertical-align:baseline;">Per 42 U.S.C.§ 4370m-2(c)(2)(F), BLM is required to provide an alternative completion date and an initial explanation for the missed completion date. BLM has provided the initial explanation for the missed date and is providing October 14, 2026 as an alternative completion date and changes the scoping date to November 12, 2026</span><span style="border-width:0px;color:black;font:inherit;margin:0px;padding:0px;vertical-align:baseline;">.</span></em></div>
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
New Milestone
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Current Target Date:
Response Date
Reporting Agency