USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Endangered Species Act Consultation (NOAA-NMFS): ESA Consultation Request Package Submitted (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 05/19/2023 for ESA Consultation Request Package Submitted (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned
POC Name:
Julie Crocker
POC Title:
Branch Chief

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
  • Monthly Status Report for May 2024:
    Additional information related to dredging for the cable route was received and work continued on the consultation in May towards completion of the consultation. The final milestone was moved from May 31 to June 18.  The consultation is anticipated to conclude on the June new 18 milestone date.
  • Monthly Status Report for April 2024:
    Additional information related to dredging for the cable route was received and work continues on the consultation in April towards completion of the consultation.
  • Monthly Status Report for March 2024:
    Additional information related to dredging for the cable route was still outstanding at the beginning of the month. Sponsor submittal anticipated by the end of the month. The information is required for the ESA consultation.  
  • Monthly Status Report for February 2024:
    There is ongoing coordination between agencies and the sponsor to ensure information sufficient to conclude consultation.
  • Monthly Status Report for January 2024:
    NMFS deemed the BA complete on Jan 3, 2024 meeting the dashboard milestone. NMFS is on track to complete the subsequent May 31, 2024 milestone, to conclude ESA consultation.
  • Monthly Status Report for December 2023:
    BOEM submitted a revised Biological Assessment to NMFS on Dec 15, 2023. NMFS's review of the revised BA is ongoing, target completion date of Jan 3, 2024 to deem package complete is on track.
  • Monthly Status Report for November 2023:
    Alternative milestone shifting from Dec 4, 2023 to Jan 3, 2024 to allow BOEM time to gather information from developer and update the consultation documents. Issues include: inconsistency with USACE permit application (which was submitted after most of the consultation documents were written); clarifications about ports and O&M facility; need more info from US Wind about disposition of dredged material.
  • Monthly Status Report for October 2023:
    BOEM and NMFS coordinated regarding needed information to update consultation documents. BOEM is coordinating with the sponsor to collect required information.
  • Monthly Status Report for September 2023:
    BOEM and NMFS coordinated regarding needed information to update consultation documents. BOEM is coordinating with the sponsor to collect required information.
  • Monthly Status Report for August 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Monthly Status Report for July 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Monthly Status Report for June 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Non-conformance Explanation:
    The original date entered into the dashboard for this milestone was misaligned with BOEM's nominal schedule. In the nominal schedule, this milestone typically is concurrent with the start of the NMFS's DEIS review. That date is anticipated to be June 2, 2023, not May 19 as previously indicated.
Current Target Date:
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone
ESA Consultation Request Package Submitted (Agency Action)
  • Monthly Status Report for May 2024:
    Additional information related to dredging for the cable route was received and work continued on the consultation in May towards completion of the consultation. The final milestone was moved from May 31 to June 18.  The consultation is anticipated to conclude on the June new 18 milestone date.
  • Monthly Status Report for April 2024:
    Additional information related to dredging for the cable route was received and work continues on the consultation in April towards completion of the consultation.
  • Monthly Status Report for March 2024:
    Additional information related to dredging for the cable route was still outstanding at the beginning of the month. Sponsor submittal anticipated by the end of the month. The information is required for the ESA consultation.  
  • Monthly Status Report for February 2024:
    There is ongoing coordination between agencies and the sponsor to ensure information sufficient to conclude consultation.
  • Monthly Status Report for January 2024:
    NMFS deemed the BA complete on Jan 3, 2024 meeting the dashboard milestone. NMFS is on track to complete the subsequent May 31, 2024 milestone, to conclude ESA consultation.
  • Monthly Status Report for December 2023:
    BOEM submitted a revised Biological Assessment to NMFS on Dec 15, 2023. NMFS's review of the revised BA is ongoing, target completion date of Jan 3, 2024 to deem package complete is on track.
  • Monthly Status Report for November 2023:
    Alternative milestone shifting from Dec 4, 2023 to Jan 3, 2024 to allow BOEM time to gather information from developer and update the consultation documents. Issues include: inconsistency with USACE permit application (which was submitted after most of the consultation documents were written); clarifications about ports and O&M facility; need more info from US Wind about disposition of dredged material.
  • Monthly Status Report for October 2023:
    BOEM and NMFS coordinated regarding needed information to update consultation documents. BOEM is coordinating with the sponsor to collect required information.
  • Monthly Status Report for September 2023:
    BOEM and NMFS coordinated regarding needed information to update consultation documents. BOEM is coordinating with the sponsor to collect required information.
  • Monthly Status Report for August 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Monthly Status Report for July 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Monthly Status Report for June 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Non-conformance Explanation:
    The original date entered into the dashboard for this milestone was misaligned with BOEM's nominal schedule. In the nominal schedule, this milestone typically is concurrent with the start of the NMFS's DEIS review. That date is anticipated to be June 2, 2023, not May 19 as previously indicated.
Current Target Date:
Project

PROJECT WEBSITE: http://www.uswindinc.com

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
01/03/2025

9 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Description:

The Maryland Offshore Wind Project involves construction of a renewable energy generation facility and the associated electricity transmission infrastructure to connect the generation to the regional electric grid. 

US Wind is proposing the development and eventual decommissioning of the Maryland Offshore Wind Project (the Project), an offshore wind energy project (including an Operations and Maintenance Facility) of up to approximately 2 gigawatts of nameplate capacity within OCS-A 0490 (the Lease). The Lease area covers 79,707 acres with the western edge located approximately 18.5 km (11.5 miles) off the coast of Maryland on the Outer Continental Shelf.

Under a Project Design Envelope (PDE) approach, the Project could include as many as 121 wind turbine generators (WTG), up to four offshore substations (OSS), and one meteorological tower (Met Tower) in the Lease area, with a total of 126 structure in a gridded array pattern distributed across the Lease area. The gridded array comprises 13 east-west rows with 0.87 mile spacing between structures, and 18 columns oriented approximately north-northeast to south-southwest with 1.17 mile spacing. Inter-array cables would run in a radial fashion from the WTGs toward the OSS locations. The Met Tower is proposed in a location along the southern edge of the Lease area.

Up to 4 offshore export cables are included in the PDE. The export cables consist of an offshore portion, the Offshore Export Cables, from the Lease area to the landing location, through a transition vault to the onshore portion, and the Onshore Export Cables that connect to the Point of Interconnection (POI). The preferred route of the offshore export cable, known as Offshore Export Cable Corridor 1, would exit the Lease area from the northwestern portion of the Lease area, and traverse northeasterly to shore making landfall south of the Indian River Inlet at 3R’s Beach in the Delaware Seashore State Park. From there the onshore export submarine cables would extend through Indian River Bay via Onshore Export Cable Corridor 1 and connect to the POI at the Delmarva Power and Light Indian River Substation near Millsboro, Delaware. Additional options within the PDE include the offshore export cables making landfall at the Tower Road parking lot, north of Indian River inlet, and crossing over land to the Indian River Substation or alternate POIs. The PDE also includes land-based cable corridors, if a terrestrial route is pursued, which would be co-located in existing rights-of-way.

The Operations and Maintenance Facility (O&M Facility) is proposed to be in Ocean City, Maryland, and would include a 15,000 square foot combined office and warehouse building with associated parking, outdoor storage, and crew comfort and support areas to stage operations and maintenance personnel. The O&M Facility would include crew transfer vessel (CTV) quayside and berthing areas, and would also house a Marine Coordination Center, which would serve to monitor the status of the WTGs and OSSs via SCADA systems, plan maintenance operations and dispatch CTVs, monitor marine activity in the Project area, coordinate drills and exercises, and communicate with outside agencies.

 

field_status
System Comments
Agency Milestone Date of 05/19/2023 for ESA Consultation Request Package Submitted (Agency Action) has passed by 1 business days
Approver Comments
<p>Additional information related to dredging for the cable route was received and work continued on the consultation in May towards completion of the consultation. The final milestone was moved from May 31 to June 18. &nbsp;The consultation is anticipated to conclude on the June new 18 milestone date.</p>
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
Agency Notified Date
New Milestone
ESA Consultation Request Package Submitted (Agency Action)
  • Monthly Status Report for May 2024:
    Additional information related to dredging for the cable route was received and work continued on the consultation in May towards completion of the consultation. The final milestone was moved from May 31 to June 18.  The consultation is anticipated to conclude on the June new 18 milestone date.
  • Monthly Status Report for April 2024:
    Additional information related to dredging for the cable route was received and work continues on the consultation in April towards completion of the consultation.
  • Monthly Status Report for March 2024:
    Additional information related to dredging for the cable route was still outstanding at the beginning of the month. Sponsor submittal anticipated by the end of the month. The information is required for the ESA consultation.  
  • Monthly Status Report for February 2024:
    There is ongoing coordination between agencies and the sponsor to ensure information sufficient to conclude consultation.
  • Monthly Status Report for January 2024:
    NMFS deemed the BA complete on Jan 3, 2024 meeting the dashboard milestone. NMFS is on track to complete the subsequent May 31, 2024 milestone, to conclude ESA consultation.
  • Monthly Status Report for December 2023:
    BOEM submitted a revised Biological Assessment to NMFS on Dec 15, 2023. NMFS's review of the revised BA is ongoing, target completion date of Jan 3, 2024 to deem package complete is on track.
  • Monthly Status Report for November 2023:
    Alternative milestone shifting from Dec 4, 2023 to Jan 3, 2024 to allow BOEM time to gather information from developer and update the consultation documents. Issues include: inconsistency with USACE permit application (which was submitted after most of the consultation documents were written); clarifications about ports and O&M facility; need more info from US Wind about disposition of dredged material.
  • Monthly Status Report for October 2023:
    BOEM and NMFS coordinated regarding needed information to update consultation documents. BOEM is coordinating with the sponsor to collect required information.
  • Monthly Status Report for September 2023:
    BOEM and NMFS coordinated regarding needed information to update consultation documents. BOEM is coordinating with the sponsor to collect required information.
  • Monthly Status Report for August 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Monthly Status Report for July 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Monthly Status Report for June 2023:
    NMFS anticipates a delay of about a month in the ESA and EFH consultation submissions due to the delay in receipt of the consultation requests resulting from changes to the project activities. This delay has cascading delays on subsequent ESA and EFH milestones.
  • Non-conformance Explanation:
    The original date entered into the dashboard for this milestone was misaligned with BOEM's nominal schedule. In the nominal schedule, this milestone typically is concurrent with the start of the NMFS's DEIS review. That date is anticipated to be June 2, 2023, not May 19 as previously indicated.
Current Target Date:
Response Date