USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-06-2023 11-03-2023 01-03-2024 Yes
ESA Consultation Concludes (Agency Action) 03-04-2024 04-01-2024 06-18-2024 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-06-2023 11-03-2023 01-03-2024 Yes
ESA Consultation Concludes (Agency Action) 03-04-2024 04-01-2024 06-18-2024 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-06-2023 11-03-2023 01-03-2024 Yes
ESA Consultation Concludes (Agency Action) 03-04-2024 04-01-2024 05-31-2024 No
Planned
BOEM needs more time to work on the BA and coordinate activities with the USACE.  
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-06-2023 11-03-2023 01-03-2024 No
ESA Consultation Concludes (Agency Action) 03-04-2024 04-01-2024 05-31-2024 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-06-2023 11-03-2023 12-04-2023 No
ESA Consultation Concludes (Agency Action) 03-04-2024 04-01-2024 05-01-2024 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-06-2023 11-03-2023 11-03-2023 No
ESA Consultation Concludes (Agency Action) 03-04-2024 04-01-2024 04-01-2024 No
Planned
The original date entered into the dashboard for this milestone was misaligned with BOEM's nominal schedule. In the nominal schedule, this milestone is typically concurrent with the start of the NMFS's DEIS review. That date is anticipated to be June 2, 2023, not May 19 as previously indicated.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-21-2023 05-19-2023 06-02-2023 No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-06-2023 11-03-2023 --- No
ESA Consultation Concludes (Agency Action) 03-04-2024 04-01-2024 --- No
Planned
The applicant submitted a revised ITA application on 1/24/23.  However, there are still inconsistencies and there are additional questions based on review of the 1/24 submittal.  Therefore, the MMPA dates are being extended to allow time to address the inconsistencies in the ITA application.  Due to dependencies between the MMPA and ESA milestones, this requires the second two ESA milestones to be shifted. Due to relationships between the ESA and EFH milestones, the second two EFH milestones also need to be shifted.  BOEM indicated that 5/19/23 would be when they would submit the request for ESA and EFH consultations. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 04-21-2023 05-19-2023 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 10-06-2023 11-03-2023 --- No
ESA Consultation Concludes (Agency Action) 03-04-2024 04-01-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 04-21-2023 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) --- 10-06-2023 --- No
ESA Consultation Concludes (Agency Action) --- 03-04-2024 --- No