USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): ESA Consultation Request Package Submitted (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 03/07/2025 for ESA Consultation Request Package Submitted (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Planned

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
  • Monthly Status Report for April 2025:
    BOEM is on track to meet the milestone completion date.  
  • Non-conformance Explanation:
    BOEM was unable to conform with this milestone for Atlantic Shores North (ASOW N) due to uncertainty in the project timeline.  The Presidential Memorandum, Temporary Withdrawal of All Areas on the Outer Continental Shelf from Offshore Wind Leasing and Review of the Federal Government’s Leasing and Permitting Practices for Wind Projects, discusses the development of a comprehensive assessment and review of Federal wind leasing and permitting practices.  Further guidance as to how the assessment will impact the project is necessary to conform to this milestone.
Alternative Completion Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Alternative Completion Date:
ESA Consultation Concludes (Agency Action)
Alternative Completion Date:
Milestone
ESA Consultation Request Package Submitted (Agency Action)
  • Monthly Status Report for April 2025:
    BOEM is on track to meet the milestone completion date.  
  • Non-conformance Explanation:
    BOEM was unable to conform with this milestone for Atlantic Shores North (ASOW N) due to uncertainty in the project timeline.  The Presidential Memorandum, Temporary Withdrawal of All Areas on the Outer Continental Shelf from Offshore Wind Leasing and Review of the Federal Government’s Leasing and Permitting Practices for Wind Projects, discusses the development of a comprehensive assessment and review of Federal wind leasing and permitting practices.  Further guidance as to how the assessment will impact the project is necessary to conform to this milestone.
Current Target Date:
Project

PROJECT WEBSITE: Atlantic Shores Offshore Wind

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/11/2027

0 out of 11

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Ocean Energy Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

No icon

Department of Defense, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Environmental Protection Agency

Environmental Protection Agency

Description:

Atlantic Shores Offshore Wind, LLC (“Atlantic Shores”) proposes to construct, operate, and maintain the Atlantic Shore North Project (the “Project”; “Atlantic Shores North”), an offshore renewable wind energy facility in Lease Area OCS-A 0549, which is approximately 7.8 statute miles (mi) (12.6 kilometers [km]) from the New Jersey (NJ) shoreline and approximately 60 miles (96.6 km) from the New York State (NY) Coast.

The Lease Area layout is designed to maximize offshore renewable wind energy production while minimizing effects on existing marine uses. The structures will be aligned in a uniform grid with multiple lines of orientation allowing straight transit through the Lease Area. Within the Lease Area, the WTGs and OSSs will be connected by inter-array cables and/or inter-link cables. Energy from the OSSs will be delivered to shore by buried export cables that will be located within designated Export Cable Corridors (ECCs) from the Lease Area through Federal as well as New Jersey and/or New York State waters to landfall sites on the New Jersey and/or New York coastlines.

Atlantic Shores will use horizontal directional drilling (HDD) technology to install the export cables from the end of the ECCs to the landfall sites to minimize impacts to the intertidal and nearshore habitats and ensure stable burial of the cables. From each landfall site, the onshore interconnection cables will travel underground primarily along existing roadways and utility rights-of-way (ROWs) to new or existing onshore substation and/or converter station sites.

The Executive Director granted a Bureau of Ocean Energy Management request to extend the COP, NEPA, Section 106, ESA, EFH, MMPA, Section 10/404, Section 408, NPDES, and OCS Air Permit completion dates on January 2, 2025. The Executive Director determination is posted here.

field_status
System Comments
Agency Milestone Date of 03/07/2025 for ESA Consultation Request Package Submitted (Agency Action) has passed by 1 business days
Approver Comments
<p>BOEM is on track to meet the milestone completion date.&nbsp;&nbsp;</p>
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
Agency Notified Date
New Milestone
ESA Consultation Request Package Submitted (Agency Action)
  • Monthly Status Report for April 2025:
    BOEM is on track to meet the milestone completion date.  
  • Non-conformance Explanation:
    BOEM was unable to conform with this milestone for Atlantic Shores North (ASOW N) due to uncertainty in the project timeline.  The Presidential Memorandum, Temporary Withdrawal of All Areas on the Outer Continental Shelf from Offshore Wind Leasing and Review of the Federal Government’s Leasing and Permitting Practices for Wind Projects, discusses the development of a comprehensive assessment and review of Federal wind leasing and permitting practices.  Further guidance as to how the assessment will impact the project is necessary to conform to this milestone.
Current Target Date:
Response Date