Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-06-2025 03-07-2025 06-05-2025 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-24-2025 11-07-2025 02-06-2026 No
ESA Consultation Concludes (Agency Action) 02-06-2026 04-06-2026 07-06-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-06-2025 03-07-2025 06-05-2025 No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-24-2025 11-07-2025 02-06-2026 No
ESA Consultation Concludes (Agency Action) 02-06-2026 04-06-2026 07-06-2026 No
Planned
EDD completed 1/2/25 - typo date entered wrong as 3/30/26.  It should be 4/6/26. Corrected 1/8/25 to April date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-06-2025 03-07-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-24-2025 11-07-2025 --- No
ESA Consultation Concludes (Agency Action) 02-06-2026 04-06-2026 --- No
Planned
Milestone date for publication of the Final EIS date must allow adequate time for incorporation of the findings of the ESA consultation into the Final EIS , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-06-2025 03-07-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-24-2025 11-07-2025 --- No
ESA Consultation Concludes (Agency Action) 02-06-2026 03-30-2026 --- No
Planned
Transcription error in the first milestone for FWS. The first milestone should be 6/6 on the dashboard it is 2/6. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-06-2025 06-06-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-24-2025 09-24-2025 --- No
ESA Consultation Concludes (Agency Action) 02-06-2026 02-06-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 02-06-2025 02-06-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 09-24-2025 09-24-2025 --- No
ESA Consultation Concludes (Agency Action) 02-06-2026 02-06-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- --- --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- --- --- No
ESA Consultation Concludes (Agency Action) --- --- --- No