USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Portions of this site may be affected due to a lapse in appropriations and associated shutdown/furloughs. Please monitor this page for updates on site availability and operating status.

Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 03-11-2021 03-11-2021 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 01-30-2022 01-30-2022 --- No
Publication of Public Notice (Agency Action) 02-15-2022 02-15-2022 --- No
Final Verification/Permit Decision Rendered (Agency Action) 06-15-2022 06-15-2022 --- No