Environmental Impact Statement (EIS)

Project Name: Responsible Agency:
Federal Energy Regulatory Commission
Status:
Cancelled
POC Name:
Tim Konnert
POC Title:
Branch Chief

Description:

On December 9, 2021, Commission staff issued a letter dismissing, without prejudice, the license application for the project.  On January 7, 2022, the project sponsor filed a request for rehearing or, in the alternative, motion for temporary stay of dismissal of license application.  On March 24, 2022, the Commission issued an order sustaining the result of the December 9, 2021 order and denying the motion for temporary stay. 

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Current Target Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Current Target Date: