Planned
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PLANNED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
PENDING
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Water Resources
CATEGORY
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
Description:
FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): ESA Consultation Request Package Submitted (Agency Action)
Triggered missed date from extending ESA Consultation Request Package Submitted (Agency Action) within 30 days of its current target date which was 02/06/2025 and extended to 03/06/2025
FAST-41 Missed Date:Endangered Species Act Consultation (DOI-FWS): ESA Consultation Request Package Submitted (Agency Action)
Triggered missed date from extending ESA Consultation Request Package Submitted (Agency Action) within 30 days of its current target date which was 02/06/2025 and extended to 03/06/2025
FAST-41 Missed Date:Section 106 Review: Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action)
Agency Milestone Date of 01/31/2025 for Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) has passed by 1 business days
FAST-41 Missed Date:Section 106 Review: Consultation initiated with SHPO/THPO (Agency Action)
Agency Milestone Date of 01/30/2025 for Consultation initiated with SHPO/THPO (Agency Action) has passed by 1 business days