Permitting Action Modification History

Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 11-20-2026 11-20-2026 --- No
Scoping (Agency Action) 12-21-2026 12-21-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 11-19-2027 11-19-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 11-19-2027 11-19-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 11-20-2026 11-20-2026 --- No
Scoping (Agency Action) 12-21-2026 12-21-2026 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 11-19-2027 11-19-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 11-19-2027 11-19-2027 --- No