FAST-41 Missed Date:Use Authorization (DOI-BOR): Application deemed complete (Agency Action)

Submitted by Anonymous on

Agency Milestone Date of 09/18/2026 for Application deemed complete (Agency Action) has passed by 1 business days

Action
Project Name: Responsible Agency:
Bureau of Reclamation
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Shane Hunt
POC Title:
NEPA Policy Lead
POC Email:

Description:

This milestone is for a BOR Use Authorization for Phase II of the Navajo Nation Department of Education (NN DOE) project as assessed by the NN DOE Phase II Environmental Assessment. The proposed project would serve the 11 Navajo communities; starting with San Juan Chapter, Bloomfield to Counselor and Huerfano, Crownpoint, Lake Valley, White Rock, Becenti, Rock Springs, Bread Springs, Casamero Lake, Churchrock, Pinedale, Mariano Lake, and Pueblo Pintado. 

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Application deemed complete (Agency Action)
Current Target Date:
Final decision/agency action (Agency Action)
Current Target Date:

Additional Milestones:

Additional Milestones
All outstanding application materials submitted (Applicant Action)
Completed Date:
Milestone
Application deemed complete (Agency Action)
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/19/2026

5 out of 9

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Interior

Department of the Interior, Bureau of Reclamation

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The Navajo Nation Department of Education proposes to deploy a reliable, affordable, scalable, and future-proofed broadband network that bridges the digital divide for the foreseeable future in some of the most remote, isolated, high-cost, and difficult to serve areas of the United States. The Navajo Nation Department of Education E-Rate Funded Broadband Project consists of constructing approximately 323 miles of middle mile fiber optic network on the Navajo Nation to connect 17 Head Start entities and 33 libraries with high-speed Internet connectivity to speeds of 1 Gbps or greater.

The Executive Director granted a Bureau of Indian Affairs request to extend the NEPA; Section 106; Right-of-Way (BLM); Right-of-Way (BIA); Use Authorization (BOR); and Endangered Species Act (FWS) completion dates on March 31, 2025. The Executive Director determination is posted here.

The project proponent is developing the project in phases. Phase I would provide internet service from Ya’ta’hey to San Juan Chapter, New Mexico, as considered in the Ya’ta’hey to San Juan  Chapter, New Mexico Fiber Optic Broadband Cable Navajo Nation Division of Education Environmental Assessment (EA-26-012726). Phase II of the proposed project would serve the 11 Navajo communities; starting with San Juan Chapter, Bloomfield to Counselor and Huerfano, Crownpoint, Lake Valley, White Rock, Becenti, Rock Springs, Bread Springs, Casamero Lake, Churchrock, Pinedale, Mariano Lake, and Pueblo Pintado. 

The Executive Director granted a Bureau of Indian Affairs request to extend the Right-of-Way (BLM); Right-of-Way (BIA); and Use Authorization (BOR) in June 2026. The Executive Director determination is posted here.

field_status
System Comments
Agency Milestone Date of 09/18/2026 for Application deemed complete (Agency Action) has passed by 1 business days
Previous Action Status
New Action Status
Missed Date Process
Yes
Missed Date Triggered by Extension
No
New Milestone
Application deemed complete (Agency Action)
Current Target Date:
Response Date
Reporting Agency