FAST-41 Missed Date:Environmental Assessment (EA): Issuance of a Final EA (Agency Action)
Agency Milestone Date of 02/11/2022 for Issuance of a Final EA (Agency Action) has passed by 1 business days
Agency Milestone Date of 02/11/2022 for Issuance of a Final EA (Agency Action) has passed by 1 business days
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
02/28/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Highway Administration
Other Agencies with Actions or Authorizations:
States
Department of the Army, US Army Corps of Engineers - Regulatory
Triggered missed date from extending Completeness determination (Agency Action) within 30 days of its current target date which was 08/03/2022 and extended to 08/15/2022
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/31/2025
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Surface Transportation
CATEGORY
LEAD AGENCY
California, CalTrans