Permitting Action Modification History
Modifications on 10/06/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-23-2025 | 04-29-2027 | No |
Modifications on 04/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-23-2025 | 10-30-2026 | No |
Modifications on 02/20/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-23-2025 | 04-30-2026 | No |
Modifications on 01/21/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-23-2025 | 02-20-2026 | No |
Modifications on 12/29/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-23-2025 | 12-22-2025 | No |
Modifications on 12/22/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-23-2025 | 02-20-2026 | No |
Modifications on 09/29/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-23-2025 | 12-22-2025 | No |
Modifications on 05/23/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-23-2025 | --- | No |
Modifications on 02/26/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 06-25-2025 | --- | No |
Modifications on 04/23/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 03-27-2025 | --- | No |
Modifications on 10/24/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | Yes |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | Yes |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-29-2024 | --- | No |
Modifications on 10/24/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Initial application received (Applicant Action) | 10-31-2022 | 10-31-2022 | --- | No |
| Completed application received (Applicant Action) | 09-29-2023 | 09-29-2023 | --- | No |
| Issuance of final decision/ permit approval (Agency Action) | 09-29-2024 | 09-29-2024 | --- | No |