In Progress

Project page icon
In Progress

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
09/21/2023

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

Project Name: Responsible Agency:

FAST-41 Missed Date:Environmental Impact Statement (EIS): Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)

Triggered missed date from extending Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) within 30 days of its current target date which was 06/02/2023 and extended to 07/21/2023

Project Name: Responsible Agency:
Project Name: Responsible Agency:

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Complete

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
COMPLETE

icon_calendar

COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/15/2023

2 out of 2

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Aviation

SECTOR
Aviation

Project Category

CATEGORY

Department of Transportation

LEAD AGENCY
Department of Transportation, Federal Aviation Administration

Description:

Project Name: Responsible Agency: