FAST-41 Missed Date: Section 10 Rivers and Harbors Act of 1899 and Section 404 Clean Water Act
Final Required Milestone Date of 04/24/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 04/24/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 04/20/2020 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 12/18/2019 for Section 106 consultation concluded has passed by 5 business days
Final Required Milestone Date of 02/27/2020 for Issuance of decision for permit/approval has passed by 5 business days
Final Required Milestone Date of 09/30/2019 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 09/30/2019 for Final Verification/Permit Decision Rendered has passed by 5 business days
Final Required Milestone Date of 12/31/2019 for Issuance of decision for permit/approval has passed by 5 business days
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Aviation
CATEGORY
LEAD AGENCY
Department of Transportation, Federal Aviation Administration