FAST-41 Missed Date:Environmental Impact Statement (EIS): Scoping (Agency Action)
Agency Milestone Date of 03/31/2026 for Scoping (Agency Action) has passed by 1 business days
Agency Milestone Date of 03/31/2026 for Scoping (Agency Action) has passed by 1 business days
Agency Milestone Date of 03/31/2026 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
PROJECT WEBSITE:
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/20/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
LEAD AGENCY
Department of Agriculture, US Forest Service
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Fish and Wildlife Service
Department of the Army, US Army Corps of Engineers - Regulatory
Triggered missed date from extending Section 106 consultation concluded (Agency Action) within 30 days of its current target date which was 03/27/2026 and extended to 04/10/2026