Agency Milestone Date of 03/31/2026 for Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) has passed by 1 business days
Milestones:
-
Monthly Status Report for November 2026:The Sponsor continues to submit updated information based on their Feasibility Study; the DEIS and FEIS interim milestones will change due to this new information, but the final ROD milestone will stay the same. Regular coordination with BLM and the State agencies continues as well as with the other Federal agencies. All partners for the project have been made aware of the review windows for products related the EIS so that they can appropriately prioritize this project along with their other workload during the timeline for Black Pine Gold.
-
Monthly Status Report for October 2026:The Sponsor's feasibility study was released in September 2026 and includes new information that may result in changes to permitting timelines for the State and Federal actions on the dashboard. Close coordination between the Sponsor, contractor, Forest, State, other Federal agencies, and the Permitting Council is being conducted to ensure the appropriate risks are considered in order to meet the 2-year EIS requirement. A new, modified alternative is being considered for the EIS which would incorporate analysis that has been performed for the different resource areas in order to capture efficiencies during the NEPA process. Some interim milestone dates for State and Federal actions may shift but the overall mandated 2-year NEPA deadline will not change.
-
Monthly Status Report for September 2026:Close coordination and regular communication continues with the State of Idaho for their actions and milestones on the project timeline as evidenced by the on-time completion of the Preliminary Design Review application package for the cyanidation permit. Approximately half of the resource area reports for the internal Preliminary Draft Environmental Impact Statement (DEIS), chapter 3 analysis, have been reconciled with final revisions, working towards the public release of the DEIS in February 2027. Recurring meetings with the State and Federal Agencies ensures thorough communication on where the project stands on the project timeline, current issues to work through, and pertinent updates for awareness as a whole.
-
Monthly Status Report for August 2026:Milestones for the project continue to be met on schedule for the FAST-41 timelines: the applicant submitted the Preliminary Design Report (PDR) to the State of Idaho Department of Environmental Quality (DEQ) for the cyanidation permit; the Bald and Golden Eagle Protection Permit application was confirmed received by US Fish & Wildlife Service for processing; and Federal and State leadership has met with the Idaho State Historic Preservation Office for upcoming submittals of review packages. Surveys on site have concluded or are close to finishing, which will support the resource specific narratives being drafted for the eventual EIS.
-
Monthly Status Report for July 2026:The Sponsor has chosen a strategy to pursue an existing option with US Fish & Wildlife Service for compliance with the Bald and Golden Eagle Protection Permit to ensure timely milestones are met and will not obstruct the overall project timeline. The third-party NEPA contractors continue to develop resource reports related to the overall analysis needed during the development of the EIS.
-
Monthly Status Report for June 2026:The project’s 30-day comment period ended May 4, 2026, in which 3 alternatives were identified to be analyzed during the NEPA process to meet the 2-year completion date. The Sponsor continues to work with the US Fish & Wildlife Service to find solutions for compliance with the Bald and Golden Eagle Protection Permit to ensure timely milestones are met and will not obstruct the overall project timeline.
-
Monthly Status Report for May 2026:USDA continues to closely monitor and coordinate with the Forest Service, the State of Idaho, and the Sponsor to ensure action milestones for the project are adequately tracked for meeting the EIS 2-year timeline requirement. Scoping was successfully begun by the Forest Service hosting a virtual and an in-person open house in addition to fielding public comments. The BLM successfully completed an interim milestone, Completed Application Received, under the Right-of-Way Authorization action.
-
Non-conformance Explanation:While the Forest Service started the review and approval process with adequate time, there were legal concerns identified by USDA general council office that required multiple passbacks between the regional and national staff delaying final submission and briefings to senior leadership. USDA is using this missed milestone to review internal review and approval processes to account for areas to streamline and where improvements will be proposed and implemented.
-
Monthly Status Report for November 2026:The Sponsor continues to submit updated information based on their Feasibility Study; the DEIS and FEIS interim milestones will change due to this new information, but the final ROD milestone will stay the same. Regular coordination with BLM and the State agencies continues as well as with the other Federal agencies. All partners for the project have been made aware of the review windows for products related the EIS so that they can appropriately prioritize this project along with their other workload during the timeline for Black Pine Gold.
-
Monthly Status Report for October 2026:The Sponsor's feasibility study was released in September 2026 and includes new information that may result in changes to permitting timelines for the State and Federal actions on the dashboard. Close coordination between the Sponsor, contractor, Forest, State, other Federal agencies, and the Permitting Council is being conducted to ensure the appropriate risks are considered in order to meet the 2-year EIS requirement. A new, modified alternative is being considered for the EIS which would incorporate analysis that has been performed for the different resource areas in order to capture efficiencies during the NEPA process. Some interim milestone dates for State and Federal actions may shift but the overall mandated 2-year NEPA deadline will not change.
-
Monthly Status Report for September 2026:Close coordination and regular communication continues with the State of Idaho for their actions and milestones on the project timeline as evidenced by the on-time completion of the Preliminary Design Review application package for the cyanidation permit. Approximately half of the resource area reports for the internal Preliminary Draft Environmental Impact Statement (DEIS), chapter 3 analysis, have been reconciled with final revisions, working towards the public release of the DEIS in February 2027. Recurring meetings with the State and Federal Agencies ensures thorough communication on where the project stands on the project timeline, current issues to work through, and pertinent updates for awareness as a whole.
-
Monthly Status Report for August 2026:Milestones for the project continue to be met on schedule for the FAST-41 timelines: the applicant submitted the Preliminary Design Report (PDR) to the State of Idaho Department of Environmental Quality (DEQ) for the cyanidation permit; the Bald and Golden Eagle Protection Permit application was confirmed received by US Fish & Wildlife Service for processing; and Federal and State leadership has met with the Idaho State Historic Preservation Office for upcoming submittals of review packages. Surveys on site have concluded or are close to finishing, which will support the resource specific narratives being drafted for the eventual EIS.
-
Monthly Status Report for July 2026:The Sponsor has chosen a strategy to pursue an existing option with US Fish & Wildlife Service for compliance with the Bald and Golden Eagle Protection Permit to ensure timely milestones are met and will not obstruct the overall project timeline. The third-party NEPA contractors continue to develop resource reports related to the overall analysis needed during the development of the EIS.
-
Monthly Status Report for June 2026:The project’s 30-day comment period ended May 4, 2026, in which 3 alternatives were identified to be analyzed during the NEPA process to meet the 2-year completion date.
-
Monthly Status Report for May 2026:USDA continues to closely monitor and coordinate with the Forest Service, the State of Idaho, and the Sponsor to ensure action milestones for the project are adequately tracked for meeting the EIS 2-year timeline requirement. Scoping was successfully begun by the Forest Service hosting a virtual and an in-person open house in addition to fielding public comments. The BLM successfully completed an interim milestone, Completed Application Received, under the Right-of-Way Authorization action.
-
Non-conformance Explanation:While the Forest Service started the review and approval process with adequate time, there were legal concerns identified by USDA general council office that required multiple passbacks between the regional and national staff delaying final submission and briefings to senior leadership. USDA is using this missed milestone to review internal review and approval processes to account for areas to streamline and where improvements will be proposed and implemented.
-
Monthly Status Report for November 2026:The Sponsor continues to submit updated information based on their Feasibility Study; the DEIS and FEIS interim milestones will change due to this new information, but the final ROD milestone will stay the same. Regular coordination with BLM and the State agencies continues as well as with the other Federal agencies. All partners for the project have been made aware of the review windows for products related the EIS so that they can appropriately prioritize this project along with their other workload during the timeline for Black Pine Gold.
-
Monthly Status Report for October 2026:The Sponsor's feasibility study was released in September 2026 and includes new information that may result in changes to permitting timelines for the State and Federal actions on the dashboard. Close coordination between the Sponsor, contractor, Forest, State, other Federal agencies, and the Permitting Council is being conducted to ensure the appropriate risks are considered in order to meet the 2-year EIS requirement. A new, modified alternative is being considered for the EIS which would incorporate analysis that has been performed for the different resource areas in order to capture efficiencies during the NEPA process. Some interim milestone dates for State and Federal actions may shift but the overall mandated 2-year NEPA deadline will not change.
-
Monthly Status Report for September 2026:Close coordination and regular communication continues with the State of Idaho for their actions and milestones on the project timeline as evidenced by the on-time completion of the Preliminary Design Review application package for the cyanidation permit. Approximately half of the resource area reports for the internal Preliminary Draft Environmental Impact Statement (DEIS), chapter 3 analysis, have been reconciled with final revisions, working towards the public release of the DEIS in February 2027. Recurring meetings with the State and Federal Agencies ensures thorough communication on where the project stands on the project timeline, current issues to work through, and pertinent updates for awareness as a whole.
-
Monthly Status Report for August 2026:Milestones for the project continue to be met on schedule for the FAST-41 timelines: the applicant submitted the Preliminary Design Report (PDR) to the State of Idaho Department of Environmental Quality (DEQ) for the cyanidation permit; the Bald and Golden Eagle Protection Permit application was confirmed received by US Fish & Wildlife Service for processing; and Federal and State leadership has met with the Idaho State Historic Preservation Office for upcoming submittals of review packages. Surveys on site have concluded or are close to finishing, which will support the resource specific narratives being drafted for the eventual EIS.
-
Monthly Status Report for July 2026:The Sponsor has chosen a strategy to pursue an existing option with US Fish & Wildlife Service for compliance with the Bald and Golden Eagle Protection Permit to ensure timely milestones are met and will not obstruct the overall project timeline. The third-party NEPA contractors continue to develop resource reports related to the overall analysis needed during the development of the EIS.
-
Monthly Status Report for June 2026:The project’s 30-day comment period ended May 4, 2026, in which 3 alternatives were identified to be analyzed during the NEPA process to meet the 2-year completion date. The Sponsor continues to work with the US Fish & Wildlife Service to find solutions for compliance with the Bald and Golden Eagle Protection Permit to ensure timely milestones are met and will not obstruct the overall project timeline.
-
Monthly Status Report for May 2026:USDA continues to closely monitor and coordinate with the Forest Service, the State of Idaho, and the Sponsor to ensure action milestones for the project are adequately tracked for meeting the EIS 2-year timeline requirement. Scoping was successfully begun by the Forest Service hosting a virtual and an in-person open house in addition to fielding public comments. The BLM successfully completed an interim milestone, Completed Application Received, under the Right-of-Way Authorization action.
-
Non-conformance Explanation:While the Forest Service started the review and approval process with adequate time, there were legal concerns identified by USDA general council office that required multiple passbacks between the regional and national staff delaying final submission and briefings to senior leadership. USDA is using this missed milestone to review internal review and approval processes to account for areas to streamline and where improvements will be proposed and implemented.
PROJECT WEBSITE: Black Pine Gold Project
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/15/2028
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Mining
CATEGORY
Project Category
FAST-41 Covered Projects
LEAD AGENCY
Department of Agriculture, US Forest Service
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Interior, Bureau of Land Management
Department of the Interior, Fish and Wildlife Service
Idaho
Description:
Liberty Gold USA Inc. proposes to construct, operate, close, and reclaim the Black Pine Gold Project—an open pit, run-of-mine heap leach gold mining operation largely situated on a previously disturbed site with several existing open pits and a reclaimed legacy heap leach facility. The Black Pine Gold Project will create approximately 2,328 acres of new disturbance, which combined with existing site disturbances will result in a total disturbed footprint of approximately 3,151 acres. Planned facilities include expansion of existing pits and development of new pits using conventional open pit methods; construction of two rock storage facilities (RSFs); four temporary ore stockpiles; an engineered heap leach facility (HLF) ; an Adsorption, Desorption, and Recovery (ADR) process plant and refinery; and associated roads and pipelines. Liberty Gold will extract oxide gold and silver ore and barren rock over a 17-year mine life using conventional surface mining methods, as the deposit’s grade does not support underground mining. Run-of-mine ore will be stacked directly on the HLF. Gold and silver will be recovered via a conventional on-site heap leach circuit, and the on-site ADR/refinery will produce doré bars.
The Project is on the eastern flank of the Black Pine Mountains of southeast Idaho, approximately six miles north of the Utah border, within Cassia and Oneida Counties. The 11,162-acre Project area comprises 7,059 acres of public lands administered by the USFS, Sawtooth National Forest, Minidoka Ranger District, 3,952 acres administered by the BLM, Pocatello Field Office, and 151 acres of privately owned land held by Liberty Gold. Liberty Gold controls access and mineral interests on public lands through federal unpatented lode and placer mining claims and owns the private land within the Project area.
-
Monthly Status Report for November 2026:The Sponsor continues to submit updated information based on their Feasibility Study; the DEIS and FEIS interim milestones will change due to this new information, but the final ROD milestone will stay the same. Regular coordination with BLM and the State agencies continues as well as with the other Federal agencies. All partners for the project have been made aware of the review windows for products related the EIS so that they can appropriately prioritize this project along with their other workload during the timeline for Black Pine Gold.
-
Monthly Status Report for October 2026:The Sponsor's feasibility study was released in September 2026 and includes new information that may result in changes to permitting timelines for the State and Federal actions on the dashboard. Close coordination between the Sponsor, contractor, Forest, State, other Federal agencies, and the Permitting Council is being conducted to ensure the appropriate risks are considered in order to meet the 2-year EIS requirement. A new, modified alternative is being considered for the EIS which would incorporate analysis that has been performed for the different resource areas in order to capture efficiencies during the NEPA process. Some interim milestone dates for State and Federal actions may shift but the overall mandated 2-year NEPA deadline will not change.
-
Monthly Status Report for September 2026:Close coordination and regular communication continues with the State of Idaho for their actions and milestones on the project timeline as evidenced by the on-time completion of the Preliminary Design Review application package for the cyanidation permit. Approximately half of the resource area reports for the internal Preliminary Draft Environmental Impact Statement (DEIS), chapter 3 analysis, have been reconciled with final revisions, working towards the public release of the DEIS in February 2027. Recurring meetings with the State and Federal Agencies ensures thorough communication on where the project stands on the project timeline, current issues to work through, and pertinent updates for awareness as a whole.
-
Monthly Status Report for August 2026:Milestones for the project continue to be met on schedule for the FAST-41 timelines: the applicant submitted the Preliminary Design Report (PDR) to the State of Idaho Department of Environmental Quality (DEQ) for the cyanidation permit; the Bald and Golden Eagle Protection Permit application was confirmed received by US Fish & Wildlife Service for processing; and Federal and State leadership has met with the Idaho State Historic Preservation Office for upcoming submittals of review packages. Surveys on site have concluded or are close to finishing, which will support the resource specific narratives being drafted for the eventual EIS.
-
Monthly Status Report for July 2026:The Sponsor has chosen a strategy to pursue an existing option with US Fish & Wildlife Service for compliance with the Bald and Golden Eagle Protection Permit to ensure timely milestones are met and will not obstruct the overall project timeline. The third-party NEPA contractors continue to develop resource reports related to the overall analysis needed during the development of the EIS.
-
Monthly Status Report for June 2026:The project’s 30-day comment period ended May 4, 2026, in which 3 alternatives were identified to be analyzed during the NEPA process to meet the 2-year completion date. The Sponsor continues to work with the US Fish & Wildlife Service to find solutions for compliance with the Bald and Golden Eagle Protection Permit to ensure timely milestones are met and will not obstruct the overall project timeline.
-
Monthly Status Report for May 2026:USDA continues to closely monitor and coordinate with the Forest Service, the State of Idaho, and the Sponsor to ensure action milestones for the project are adequately tracked for meeting the EIS 2-year timeline requirement. Scoping was successfully begun by the Forest Service hosting a virtual and an in-person open house in addition to fielding public comments. The BLM successfully completed an interim milestone, Completed Application Received, under the Right-of-Way Authorization action.
-
Non-conformance Explanation:While the Forest Service started the review and approval process with adequate time, there were legal concerns identified by USDA general council office that required multiple passbacks between the regional and national staff delaying final submission and briefings to senior leadership. USDA is using this missed milestone to review internal review and approval processes to account for areas to streamline and where improvements will be proposed and implemented.