Permitting Action Modification History
Modifications on 07/30/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | 11-23-2026 | 11-23-2026 | No |
| Section 106 consultation concluded (Agency Action) | 05-14-2027 | 05-14-2027 | No |
Modifications on 04/21/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Milestone Complete? |
|---|---|---|---|
| Consultation initiated with SHPO/THPO (Agency Action) | --- | 11-23-2026 | No |
| Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) | --- | --- | No |
| Section 106 consultation concluded (Agency Action) | --- | 05-14-2027 | No |