Section 106 Review

Project Name: Responsible Agency:
Bureau of Land Management
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Participating
Status:
Cancelled
POC Name:
Sarah Mathews
POC Title:
Project Manager
POC Email:
SHPO:

California

Description:

This milestone will be paused until the proponent submits an updated Cultural survey report, biological assessment, project description and proposed action. These items were to be submitted no later than October 2019. We anticipate receiving these components between mid- January 2020 and March 2020.

**Update January 8, 2021: Milestone will remain on pause until a final report is submitted. 

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
  • Environmental Impact Statement (EIS) : Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
    - Current Target Date: 03/25/2022
Current Target Date: