Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines EFH Assessment is Complete (Agency Action) 10-06-2023 11-03-2023 02-02-2024 Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-06-2024 02-01-2024 05-02-2024 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines EFH Assessment is Complete (Agency Action) 10-06-2023 11-03-2023 02-02-2024 Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-06-2024 02-01-2024 05-02-2024 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines EFH Assessment is Complete (Agency Action) 10-06-2023 11-03-2023 02-02-2024 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-06-2024 02-01-2024 05-02-2024 No
Planned
The initial EFH Assessment was submitted to NMFS in June, 2023.  However, a revised version of the EFH Assessment was submitted in October, 2023 and additional time is needed for review and coordination of that revised Assessment, so the final two milestones are being extended.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines EFH Assessment is Complete (Agency Action) 10-06-2023 11-03-2023 01-03-2024 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-06-2024 02-01-2024 04-02-2024 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines EFH Assessment is Complete (Agency Action) 10-06-2023 11-03-2023 12-04-2023 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-06-2024 02-01-2024 03-04-2024 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-21-2023 05-19-2023 06-02-2023 Yes
NOAA determines EFH Assessment is Complete (Agency Action) 10-06-2023 11-03-2023 11-03-2023 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-06-2024 02-01-2024 02-01-2024 No
Planned
The original date entered into the dashboard for this milestone was misaligned with BOEM's nominal schedule. In the nominal schedule, this milestone is typically concurrent with the start of the NMFS's DEIS review. That date is anticipated to be June 2, 2023, not May 19 as previously indicated. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-21-2023 05-19-2023 06-02-2023 No
NOAA determines EFH Assessment is Complete (Agency Action) 10-06-2023 11-03-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-06-2024 02-01-2024 --- No
Planned
The applicant submitted a revised ITA application on 1/24/23.  However, there are still inconsistencies and there are additional questions based on review of the 1/24 submittal.  Therefore, the MMPA dates are being extended to allow time to address the inconsistencies in the ITA application.  Due to dependencies between the MMPA and ESA milestones, this requires the second two ESA milestones to be shifted. Due to relationships between the ESA and EFH milestones, the second two EFH milestones also need to be shifted.  BOEM indicated that 5/19/23 would be when they would submit the request for ESA and EFH consultations.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-21-2023 05-19-2023 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 10-06-2023 11-03-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-06-2024 02-01-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 04-21-2023 04-21-2023 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 10-06-2023 10-06-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 01-06-2024 01-04-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) --- 04-21-2023 --- No
NOAA determines EFH Assessment is Complete (Agency Action) --- 10-06-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) --- 01-06-2024 --- No