Section 408 Permit

Project Name: Responsible Agency:
US Army Corps of Engineers - Civil Works
Agency Status: Cooperating under FAST-41
Status:
Complete
POC Name:
Mike Anderson
POC Title:
Chief, Design Section, Operations Branch, Norfolk District, USACE

Description:

A Section 408 Permission may be required pursuant to Section 14 of the Rivers and Harbors Act of 1899, 33 U.S.C. 408 (Section 408).  A USACE Real Estate decision and associated Outgrant may also be required.  A determination will be made on these requirements once adequate documents from the applicant are received to support a proper evaluation of the proposed activity relative to the nearby US Army Corps of Engineers Civil Works Projects and assets.

Milestones:

Initial application submitted (Applicant Action)
Completed Date:
Milestone Details

Application was submitted ahead of schedule. The original application submittal date was 3 July 2022. Application was determined incomplete and the applicant was informed via letter of the missing information needed for a complete application on 30 June 2022. 

 

 

Completeness Determination (Agency Action)
Completed Date:
Milestone Details

The USACE is allocated 30 days from application re-submittal to determine completeness. Completeness was determined 14 days early on the re-submitted application. 

Complete application submitted (Applicant Action)
Completed Date:
Issuance of Decision (Agency Action)
Completed Date:
Milestone Details

The Corps anticipates making a permit decision on or before September 29, 2023, 120 days after BOEM's target date of June 1, 2023 for Issuance of a Record of Decision.  Should submission of any required information be delayed, the district reserves its right to adjust this Target Completion Date as necessary.