USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
Decision issued ahead of schedule. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Completeness Determination (Agency Action) 08-15-2022 08-01-2022 --- Yes
Complete application submitted (Applicant Action) 08-03-2022 07-15-2022 --- Yes
Issuance of Decision (Agency Action) 08-31-2023 01-25-2024 --- Yes
In Progress
Updated USACE decision dates based on BOEM's changes to ROD date. USACE decision dates remains at 90 days post-ROD. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Completeness Determination (Agency Action) 08-15-2022 08-01-2022 --- Yes
Complete application submitted (Applicant Action) 08-03-2022 07-15-2022 --- Yes
Issuance of Decision (Agency Action) 08-31-2023 01-29-2024 --- No
In Progress
USACE finished the completeness review early for the re-submitted application from the applicant. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete application submitted (Applicant Action) 08-03-2022 07-15-2022 --- Yes
Completeness Determination (Agency Action) 08-15-2022 08-01-2022 --- Yes
Issuance of Decision (Agency Action) 08-31-2023 08-31-2023 --- No
In Progress
Updated the original target as part of the Original Target Date Data Entry Effort.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete application submitted (Applicant Action) 08-03-2022 07-15-2022 --- Yes
Completeness Determination (Agency Action) 08-15-2022 08-15-2022 --- No
Issuance of Decision (Agency Action) 08-31-2023 08-31-2023 --- No