Permitting Action Modification History

Complete
Decision issued ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Completeness Determination (Agency Action) 08-15-2022 08-01-2022 --- Yes
Complete application submitted (Applicant Action) 08-03-2022 07-15-2022 --- Yes
Issuance of Decision (Agency Action) 08-31-2023 01-25-2024 --- Yes
In Progress
Updated USACE decision dates based on BOEM's changes to ROD date. USACE decision dates remains at 90 days post-ROD.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Completeness Determination (Agency Action) 08-15-2022 08-01-2022 --- Yes
Complete application submitted (Applicant Action) 08-03-2022 07-15-2022 --- Yes
Issuance of Decision (Agency Action) 08-31-2023 01-29-2024 --- No
In Progress
USACE finished the completeness review early for the re-submitted application from the applicant.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete application submitted (Applicant Action) 08-03-2022 07-15-2022 --- Yes
Completeness Determination (Agency Action) 08-15-2022 08-01-2022 --- Yes
Issuance of Decision (Agency Action) 08-31-2023 08-31-2023 --- No
In Progress
Updated the original target as part of the Original Target Date Data Entry Effort. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-03-2022 05-17-2022 --- Yes
Complete application submitted (Applicant Action) 08-03-2022 07-15-2022 --- Yes
Completeness Determination (Agency Action) 08-15-2022 08-15-2022 --- No
Issuance of Decision (Agency Action) 08-31-2023 08-31-2023 --- No