Endangered Species Act Consultation (DOI-FWS)

Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Complete
POC Name:
Cindy Schulz
POC Title:
Supervisor, Virginia Field Office
Action Outcome:
Biological opinion issued

Description:

This schedule is for a ESA section 7 consultation should BOEM determine the project may affect federally listed species or designated critical habitat.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
Milestone Details

FWS anticipates receiving a request for consultation and a BA with release of the DEIS. 

FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
  • Monthly Status Report for June 2023:
    On March 31, 2023, FWS determined the ESA consultation package complete.
  • Monthly Status Report for April 2023:
    USFWS confirmed that this milestone was met on 3/31/23.
  • Monthly Status Report for January 2023:
    The CVOW project NEPA schedule was delayed by four months resulting in a December 16, 2022 DEIS release date from the original planned August 2022 date. On June 29, 2022 FPISC OED published BOEM's requested date shift for the NEPA DEIS from August 2022 to December 2022.  The associated USFWS consultation date change requests have been shifted accordingly.  The previous consultation dates were associated with the previous NEPA schedule and therefore out of sync with current schedule and consultation timelines.
  • Monthly Status Report for December 2022:
    The CVOW project NEPA schedule was delayed by four months resulting in a December 16, 2022 DEIS release date from the original planned August 2022 date. On June 29, 2022 FPISC OED published BOEM's requested date shift for the NEPA DEIS from August 2022 to December 2022.  The associated USFWS consultation date change requests have been shifted accordingly.  The previous consultation dates were associated with the previous NEPA schedule and therefore out of sync with current schedule and consultation timelines. Justification was provided by BOEM on 1/23/23 with alternative completion date provided on 3/31/23.  The dashboard was updated on 1/25/23 with the nonconformance explanation and alternative completion date.
  • Non-conformance Explanation:
    The CVOW project NEPA schedule was delayed by four months resulting in a December 16, 2022 DEIS release date from the original planned August 2022 date. On June 29, 2022 FPISC OED published BOEM's requested date shift for the NEPA DEIS from August 2022 to December 2022.  The associated USFWS consultation date change requests have been shifted accordingly.  The previous consultation dates were associated with the previous NEPA schedule and therefore out of sync with current schedule and consultation timelines.
Alternative Completion Date:
Milestone Details

This date assumes that the BA with the DEIS does not need additional information. If the BA is incomplete, FWS and BOEM will adjust the schedule as needed. 

ESA Consultation Concludes (Agency Action)
  • Monthly Status Report for June 2023:
    On March 31, 2023, the FWS determined that the ESA consultation package was complete and anticipated meeting the Sep 1, 2023 milestone to conclude consultation. 
  • Monthly Status Report for May 2023:
    BOEM undertook a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompassed all NEPA and associated agency actions and milestone dates for the project, including this action. The review culminated in a request from BOEM on February 28, 2023 for an Executive Director Determination to update interim and final completion dates for multiple actions, including this action. On March 30, 2023, the Executive Director made a determination to adjust the permitting timetable as requested, with the exception of this action. Because the action was already in nonconformance, it was not modified through the ED Determination and instead followed the non-conformance protocol. The alternative completion date for this action, as set forth in the BOEM request to the Executive Director, was published on the dashboard.
  • Monthly Status Report for April 2023:
    The CVOW project NEPA schedule was delayed by four months resulting in a December 16, 2022 DEIS release date from the originally planned August 2022 date.  On June 29, 2022, FPISC-OED published BOEM's requested date shift for the NEPA DEIS from August 2022 to December 2022.  The associated USFWS consultation date change requests have been shifted accordingly.  The previous consultation dates were associated with the previous NEPA schedule and therefore out of sync with the current schedule and consultation timelines.  The second ESA consultation milestone, the "USFWS Determines the ESA Consultation Package is Complete", was completed on March 31, 2023.
  • Non-conformance Explanation:
    The CVOW project NEPA schedule was delayed by four months resulting in a December 16, 2022 DEIS release date from the original planned August 2022 date. On June 29, 2022 FPISC OED published BOEM's requested date shift for the NEPA DEIS from August 2022 to December 2022.  The associated USFWS consultation date change requests have been shifted accordingly.  The previous consultation dates were associated with the previous NEPA schedule and therefore out of sync with current schedule and consultation timelines.
Alternative Completion Date:
Milestone Details

Assumes formal consultation, with completion 135 days after receipt of a complete consultation package. FWS and BOEM will adjust the schedule if formal consultation is not needed.