USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2022 08-31-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-31-2022 09-30-2022 03-31-2023 Yes
ESA Consultation Concludes (Agency Action) 01-13-2023 03-14-2023 08-31-2023 Yes
In Progress
On 3/31/23 FWS deemed BOEM's ESA consultation package "complete", as noted in the completed Alternative Completion Date for Milestone 2: FWS determines ESA Consultation Package is Complete - Formal. On 4/27/23, BOEM provided an Addendum to its Biological Assessment. Based on new information provided in that Addendum, FWS needs additional time to complete formal consultation. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2022 08-31-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-31-2022 09-30-2022 03-31-2023 Yes
ESA Consultation Concludes (Agency Action) 01-13-2023 03-14-2023 09-01-2023 No
In Progress
The CVOW project NEPA schedule was delayed by four months resulting in a December 16, 2022 DEIS release date from the original August 2022 date. The June 29, 2022 FPISC ED determined by decision to shift the NEPA DEIS dates from August 2022 to December 2022.  The associated USFWS consultation dates have been shifted accordingly.  The previous consultation dates were  associated with the previous NEPA schedule and therefore out of sync with current schedule. ESA milestone target dates were updated to reflect interagency coordination and provide more time for the applicant in BOEM to develop a complete initiation package.   
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2022 08-31-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-31-2022 09-30-2022 03-31-2023 Yes
ESA Consultation Concludes (Agency Action) 01-13-2023 03-14-2023 08-17-2023 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2022 08-31-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-31-2022 09-30-2022 --- No
ESA Consultation Concludes (Agency Action) 01-13-2023 03-14-2023 --- No
Planned
USFWS Initial Consultation date changed to reflect over all NEPA schedule shift to DEIS NOA December 16 2022.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 08-01-2022 08-31-2022 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-31-2022 09-30-2022 --- No
ESA Consultation Concludes (Agency Action) 01-13-2023 03-14-2023 --- No