Cooperating under NEPA
Description:
A Section 408 Permission is required from the Philadelphia District pursuant to Section 14 of the Rivers and Harbors Act of 1899, 33 U.S.C. 408 (Section 408) and will evaluate the proposed activity relative to the nearby US Army Corps of Engineers Civil Works Projects and assets.
Milestones:
The 408 application was determined to be incomplete and the applicant was notified on 11/14/2022.
Applicant resubmitted 408 application on 1/20/2023. USACE determined the resubmittal to be complete on 1/25/2023
90 days following BOEM issued ROD