USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2022 10-21-2022 --- Yes
Completeness Determination (Agency Action) 11-15-2022 11-21-2022 --- Yes
Complete application submitted (Applicant Action) 01-23-2023 01-20-2023 --- Yes
Issuance of Decision (Agency Action) 12-22-2023 12-16-2024 --- Yes
In Progress
Applicant technical information delays and application resubmittal have resulted in decision postponement for the Section 408 review and the need to shift the 29 October 2024 final decision milestone to 16 December 2024.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2022 10-21-2022 --- Yes
Completeness Determination (Agency Action) 11-15-2022 11-21-2022 --- Yes
Complete application submitted (Applicant Action) 01-23-2023 01-20-2023 --- Yes
Issuance of Decision (Agency Action) 12-22-2023 12-16-2024 --- No
In Progress
The basis for USACE request to extend the final completion date for the Section 408 Permit is that these actions are dependent upon the timing of BOEM’s issuance of a FEIS and ROD to conclude its NEPA review.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2022 10-21-2022 --- Yes
Completeness Determination (Agency Action) 11-15-2022 11-21-2022 --- Yes
Complete application submitted (Applicant Action) 01-23-2023 01-20-2023 --- Yes
Issuance of Decision (Agency Action) 12-22-2023 10-29-2024 --- No
In Progress
Date needs to move 120-days after ROD (EIS milestone). The ROD date move is tied to the DEIS move date.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2022 10-21-2022 --- Yes
Completeness Determination (Agency Action) 11-15-2022 11-21-2022 --- Yes
Complete application submitted (Applicant Action) 01-23-2023 01-20-2023 --- Yes
Issuance of Decision (Agency Action) 12-22-2023 07-23-2024 --- No
In Progress
To issue this authorization USACE needs the BOEM ROD. The ROD Milestone was moved due to the delay of the DEIS.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2022 10-21-2022 --- Yes
Completeness Determination (Agency Action) 11-15-2022 11-21-2022 --- Yes
Complete application submitted (Applicant Action) 01-23-2023 01-20-2023 --- Yes
Issuance of Decision (Agency Action) 12-22-2023 12-22-2023 --- No
In Progress
To issue this authorization USACE need the BOEM ROD. The ROD Milestone was moved due to the delay of the DEIS.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2022 10-21-2022 --- Yes
Completeness Determination (Agency Action) 11-15-2022 11-21-2022 --- Yes
Complete application submitted (Applicant Action) 01-23-2023 01-20-2023 --- No
Issuance of Decision (Agency Action) 12-22-2023 12-22-2023 --- No
Planned
Applicant missed initial application date. A revised application date was provided, but the applicant submitted it a few days early. The 2nd and 3rd milestones were adjusted accordingly. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2022 10-21-2022 --- Yes
Completeness Determination (Agency Action) 11-15-2022 11-21-2022 --- No
Complete application submitted (Applicant Action) 01-23-2023 01-20-2023 --- No
Issuance of Decision (Agency Action) 12-22-2023 12-22-2023 --- No
Planned
Applicant did not provide a Section 408 application submittal on 10/15/22. Applicant updated their submittal date to 10/24/22, pushing the completeness determination (30 days after application submittal) to 11/23/22. Complete application submitted was previously blank since this is a newer milestone.  Complete application was then submitted on 10/21/2022 rather than 10/24/2022. 
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2022 10-21-2022 --- Yes
Completeness Determination (Agency Action) 11-15-2022 11-23-2022 --- No
Complete application submitted (Applicant Action) 01-23-2023 01-23-2023 --- No
Issuance of Decision (Agency Action) 12-22-2023 12-22-2023 --- No
Planned
Original Target Date Entry Effort
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 10-15-2022 10-15-2022 --- No
Completeness Determination (Agency Action) 11-15-2022 11-15-2022 --- No
Complete application submitted (Applicant Action) --- --- --- No
Issuance of Decision (Agency Action) 12-22-2023 12-22-2023 --- No