Environmental Impact Statement (EIS)

Project Name: Responsible Agency:
Bureau of Ocean Energy Management
Status:
Complete
POC Name:
Kimberly Sullivan
POC Title:
Environmental Protection Specialist
Action Outcome:
Issuance of a joint ROD

Milestones:

Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action)
Completed Date:
Scoping (Agency Action)
Completed Date:
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
  • Monthly Status Report for June 2024:
    FEIS NOA published on May 31 and BOEM is on track to meet the ROD milestone of July 1.
  • Monthly Status Report for May 2024:
    FEIS NOA on track to publish in the Federal Register on May 31. The FEIS was posted to the BOEM website a week prior to the milestone. BOEM is drafting the ROD in order to meet the July 1 ROD milestone.
  • Monthly Status Report for April 2024:
    BOEM circulated the redline response to agency comment on the preliminary FEIS back to agencies on April 8. BOEM is on track to meet the May 31 milestone.    
  • Monthly Status Report for March 2024:
    BOEM environmental review is on track to meet the May 31 milestone for the DEIS. BOEM is currently addressing agency comment on the preliminary FEIS and will circulate the redline and response to agency comments back to agencies in early April.  
  • Monthly Status Report for February 2024:
    The DEIS milestone was recently shifted to May 31, 2024 and BOEM is on track to meet the milestone. BOEM is currently addressing agency comments on the preliminary FEIS and will circulate the redline and response to agency comments back to agencies in early April, as efforts progress towards towards finalizing the environmental analysis.
  • Monthly Status Report for January 2024:
    BOEM developed a revised timetable for this project after reviewing the project schedule with the cooperating agencies and in consultation with the project sponsor. The revised timetable encompasses all remaining milestones, including milestones for this nonconformant action. While an Executive Director Determination (EDD) is not needed to update this milestone, BOEM intends to adopt the revised timetable, which was provided to the Permitting Council in an EDD request on Jan 26, 2024 and which includes this milestone; upon receipt of the EDD.
  • Monthly Status Report for December 2023:
    BOEM is undertaking a review of the permitting timetable for this project with the cooperating agencies and in consultation with the project sponsor. The review encompasses all agency actions and milestone dates for the project, including this action. The review will result in an updated permitting timetable for all actions, including this milestone.
  • Monthly Status Report for November 2023:
    Milestone completed on July 19, 2023, potential delay for subsequent milestone of FEIS due to Coastal Zone Management Act. BOEM is working with the Sponsor and NJ Department of Environmental Protection to ascertain impact.
  • Monthly Status Report for October 2023:
    Milestone completed on July 19, 2023, potential delay for subsequent milestone of FEIS due to Coastal Zone Management Act. BOEM is working with the Sponsor and NJ Department of Environmental Protection to ascertain impact.
  • Monthly Status Report for September 2023:
    Milestone Completed on July 19, 2023
  • Monthly Status Report for August 2023:
    Milestone is complete.
  • Monthly Status Report for July 2023:
    Milestone is complete. The draft EIS published in the Federal Register on May 19, 2023.
  • Monthly Status Report for June 2023:
    The availability of the draft EIS published in the Federal Register on May 19, 2023.
  • Non-conformance Explanation:
    BOEM is undertaking a comprehensive review of the permitting timetable for this project with the cooperating agencies and project sponsor. The review encompasses all NEPA and associated agency actions and milestone dates for the project, including this action. The review is expected to be completed in early May 2023, which will result in coordination with the FPISC Executive Director.
Alternative Completion Date:
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action)
Alternative Completion Date:
Issuance of Lead Agency Record of Decision (Agency Action)
Alternative Completion Date: