USCG Bridge Permit

Project Name: Responsible Agency:
US Coast Guard
Agency Status: Cooperating under FAST-41
Status:
Planned
POC Name:
Matthew Robertson
POC Title:
Bridge Management Specialist

Description:

In September 2020, the Coast Guard issued bridge permits approving the location and plans for five bridges across navigable waters of the United States. The permits are set to expire on September 11, 2025. The Coast Guard is expecting to receive applications for permit amendments to extend the time to commence and complete construction of the bridges. 

Milestones:

Navigation Data Submitted (Applicant Action)
Current Target Date:
Issued Preliminary Navigation Clearance Determination (Agency Action)
Current Target Date:
Initial Application Submitted (Applicant Action)
Current Target Date:
Milestone Details

Initial application received. Individual applications are required for each proposed crossing.

Publication of Public Notice (Agency Action)
Current Target Date:
Milestone Details

The USCG will issue public notices within 30 days of receiving the Initial Application, provided that all necessary information is provided. A 30-day comment period will follow.

Application Deemed Complete (Agency Action)
Current Target Date:
Milestone Details

The application can be deemed complete when all applicable information listed in the USCG Bridge Permit Application Guide have been received.

Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The decision is rendered within 90 days after the application is deemed complete.