Description:
In September 2020, the Coast Guard issued bridge permits approving the location and plans for five bridges across navigable waters of the United States. The permits are set to expire on September 11, 2025. The Coast Guard is expecting to receive applications for permit amendments to extend the time to commence and complete construction of the bridges.
Milestones:
Initial application received. Individual applications are required for each proposed crossing.
The USCG will issue public notices within 30 days of receiving the Initial Application, provided that all necessary information is provided. A 30-day comment period will follow.
The application can be deemed complete when all applicable information listed in the USCG Bridge Permit Application Guide have been received.
The decision is rendered within 90 days after the application is deemed complete.