FAST-41 Missed Date: Right-of-Way Authorization (DOI-BLM)

Submitted by Anonymous on

Final Required Milestone Date of 05/29/2022 for Issuance of decision for permit/approval has passed by 5 business days

Action
Project Name: Responsible Agency:
Bureau of Land Management
Agency Status: Cooperating under FAST-41
Status:
Paused
POC Name:
Sarah Mathews
POC Title:
Project Manager
POC Email:

Description:

The Bureau of Land Management (BLM) is the lead Federal agency for responding to an application for a right-of-way across federal lands under Mineral Leasing Act. The BLM right-of-way grant would include Forest Service traversed lands and Fish and Wildlife Service traversed lands. If the BLM offers a right-of-way grant to the applicant, the target date for this action will be the offer date of the right-of-way grant to the applicant for their signature.

Plan of Development(POD) is a dependency. Waiting for POD submittal to deem application complete.

 

This milestone will be paused until the proponent submits an updated Cultural survey report, biological assessment, project description and proposed action. These items were to be submitted no later than October 2019. We anticipate receiving these components between mid- January 2020 and March 2020.  

 

Milestones:

Initial application received (Agency Action)
Completed Date:
Completed application received (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:

There are no milestones to display.

There are no milestones to display.

Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Replacement of Lines 901 and 903

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

Plains Pipeline, L.P. filed a right-of-way application with the Bureau of Land Management (BLM) Bakersfield Office on January 9, 2018, for the replacement and abandonment of existing oil pipelines 901 and 903. The project spans multiple local, State and Federal jurisdictions. The proposed project consists of installation and operation of approximately 123.4 miles of replacement pipelines 901R and 903R, supporting access roads, valves, and pump stations. 

The project was paused from November 1, 2019 to January 4, 2021. Plains Pipeline, L.P. submitted an updated project description and supporting documents during this time. A Standard Individual Permit (SIP) application was submitted to the United States Army Corps of Engineers on October 5, 2020 to replace the original Nation Wide Permit (NWP) 12 Per-Construction Notification(PCN) application while the project was in paused status.

field_status
System Comments
Final Required Milestone Date of 05/29/2022 for Issuance of decision for permit/approval has passed by 5 business days
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Final decision/agency action (Agency Action)
Current Target Date: