FAST-41 Missed Date: Endangered Species Act Consultation (NOAA-NMFS)

Submitted by Anonymous on

Final Required Milestone Date of 12/22/2021 for Conclusion of ESA Consultation has passed by 5 business days

Action
Project Name: Responsible Agency:
National Oceanic and Atmospheric Administration
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Paused
POC Name:
Jay Ogawa
POC Title:
Fish Biologist
POC Email:

Description:

Section 7(a)(2) of the Endangered Species Act (ESA) requires Federal agencies to consult with NOAA Fisheries when any project or action they take might affect an ESA-listed species under NOAA Fisheries’ jurisdiction, or might affect such species’ critical habitat.  The endangered Southern California Distinct Population Segment of steelhead (Oncorhynchus mykiss) and designated critical habitat for this species exist throughout much of the area affected by the Lake Elsinore Advanced Pumped Storage Project.  The proposed action may adversely affect this resource, therefore Section 7 consultation is required.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
  • Environmental Impact Statement (EIS) : Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action)
    - Current Target Date: 07/09/2021
Current Target Date:
Milestone Details

This target timeline is dependent on receipt of a consultation request from the Federal Energy Regulatory Commission (FERC), consisting of a Biological Assessment, expected concurrent with the Notice of Availability of FERC’s DEIS.

NOAA determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
Milestone Details

This date is dependent upon NOAA Fisheries receiving sufficient information (a complete final Biological Assessment) from FERC to deem the package complete and initiate the ESA consultation.

ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone Details

The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation.  The target completion date is 135 days following the consultation initiation date for formal consultations.

Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone Details

The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation.  The target completion date is 135 days following the consultation initiation date for formal consultations.

Project

PROJECT WEBSITE: LEAPS Hydropower

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

0 out of 0

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

Description:

The Lake Elsinore Advanced Pumped Storage Project (Project No. 14227) is a proposal to construct an original pumped storage project in California.  The proposed project would consist of:  (1) a new upper reservoir (Decker Canyon) having a 200-foot-high main dam and a gross storage volume of 5,750 acre-feet, at a normal reservoir surface elevation of 2,792 feet above mean sea level; (2) a powerhouse with two reversible pump-turbine units with a total installed capacity of 500 megawatts; (3) the existing Lake Elsinore to be used as a lower reservoir; (4) about 32 miles of 500-kilovolt transmission line connecting the project to an existing transmission line owned by Southern California Edison located north of the proposed project and to an existing San Diego Gas & Electric Company transmission line located to the south.

On December 9, 2021, Commission staff issued a letter dismissing, without prejudice, the license application for the project.  Under the Commission’s regulations, parties have 30 days to file for rehearing of this dismissal.

FAST-41 Initiation Notice

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

Last updated December 27, 2021

field_status
System Comments
Final Required Milestone Date of 12/22/2021 for Conclusion of ESA Consultation has passed by 5 business days
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone Details

The final completion date is contingent upon NOAA Fisheries receiving sufficient information that NOAA Fisheries determines adequate to initiate ESA consultation.  The target completion date is 135 days following the consultation initiation date for formal consultations.