FAST-41 Postings by Agencies for Boardman to Hemingway Transmission Line

Bureau of Land Management (Posted on: )

FAST-41 Initiation Notice

FAST-41 initiation July 6, 2017

http://www.boardmantohemingway.com

Application and Supporting Documents

Original application received by BLM December 19, 2007.  Contact BLM Project Manager for additional information.

http://www.boardmantohemingway.com

Information on the status of mitigation measures
Description of the status of any litigation
Information about project-related public meetings, public hearings, and public comment periods
Description of any Federal agency action taken or decision made that materially affects the status of the project

In keeping with its mission and NEPA, BLM has established collaborative relationships with many Federal, State and local organizations to facilitate cooperative government reviews, ensure science-based decision-making, and prevent duplicative efforts. As part of this approach, BLM incorporates input from the public and affected local governments into the review process. BLM relies on this input to develop an Environmental Impact Statement (as required by 30 CFR 550.269) to support its decision-making process.

BLM NEPA - Boardman to Hemingway Project

US Army Corps of Engineers - Regulatory (Posted on: )

FAST-41 Initiation Notice

FAST-41 Initiation Notice provided by the lead agency.

Application and Supporting Documents

Application has not been received by the USACE.

Information on the status of mitigation measures

No decision has been made due to no application received 

Description of the status of any litigation

N/A

Information about project-related public meetings, public hearings, and public comment periods

None at this time.

Description of any Federal agency action taken or decision made that materially affects the status of the project

Not available at this time.

Bureau of Reclamation (Posted on: )

FAST-41 Initiation Notice

The FIN will be posted by the Lead Agency.

Application and Supporting Documents

Application and supporting documents are dependent on submittal of a final Plan of Development (POD).  A final, complete POD has not yet been received.  

Information on the status of mitigation measures

Mitigation measures were partially identified in the 2018 Record of Decision.  Final and complete mitigation measures will be dependent on submittal of a final Plan of Development (POD) and application.

Description of the status of any litigation

None.

Information about project-related public meetings, public hearings, and public comment periods

All public engagement is complete as of the 2018 ROD.

Description of any Federal agency action taken or decision made that materially affects the status of the project

Agency action (or decision) is dependent on submittal of a final Plan of Development (POD) and application.