PROJECT WEBSITE: Port of Corpus Christi's Website
All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.
ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS
ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2024
ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED
SECTOR
Ports and Waterways
CATEGORY
Project Category
FAST-41 Covered Projects
Major Infrastructure Projects
LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory
View FAST-41 Postings by Agencies
Other Agencies with Actions or Authorizations:
Department of the Army, US Army Corps of Engineers - Civil Works
Department of the Interior, Fish and Wildlife Service
Department of Commerce, National Oceanic and Atmospheric Administration
Description:
The purpose of the proposed project is to construct a channel with the capability to accomodate the transit of fully laden Very Large Crude Carriers (VLCCs) from multiple locations on Harbor Island, TX and into the Gulf of Mexico.
Milestone: Final Verification/Permit Decision Rendered
Requested extensions greater than 30 days for this Action are shown below:
Final Verification/Permit Decision Rendered by 238 days
From: 08/20/2021
To: 04/15/2022