FAST-41 Missed Date: Section 404 Clean Water Act

Submitted by Anonymous on

Final Required Milestone Date of 04/30/2021 for Final Verification/Permit Decision Rendered has passed by 5 business days

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Regulatory
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Cancelled
POC Name:
Theresa Stevens
POC Title:
Senior Project Manager

Description:

The applicant submitted a Standard Individual Permit (SIP) application on 5 OCT 2020 to replace the original NWP12 PCN/application while the project was in Paused status.

Milestones:

Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action)
Completed Date:
Milestone Details

On December 17, 2018 the applicant submitted a PCN to the Corps. A waters upload spreadsheet was requested on January 2, 2019. An additional information request was also sent to the applicant on January 7, 2019. Another information request was sent on January 24, 2019. On January 30, 2019 and February 26, 2019 the applicant requested more time (to March 8, 2019) to resubmit the PCN. No additional information was submitted on March 8, 2019. Target date for receipt of complete PCN: July 31, 2019. As of April 4, 2019 the revised PCN has not been resubmitted to the Corps and no target date has been given to the Corps by the applicant/agent.       

Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action)
Completed Date:
Milestone Details

Although a PCN was submitted in December 2018, it was incomplete (need BA and waters upload spreadsheet). The applicant expects to submit all requested additional information with a revised PCN. This milestone is dependent on the applicant submitting a complete PCN by July 31, 2019. Target date for submittal: Unknown as of April 4, 2019. Complete determination: Pending.     

Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The NWP action requires Section 106 NHPA consultation (BLM Lead Federal Agency) and a Section 7 ESA Biological Opinion from USFWS (Corps Lead Federal Agency). ESA and tribal coordination letters are drafted and pending transmittal, but cannot be completed until the submittal of a complete PCN (dependency). Both the 106 and ESA consultations are dependent on the NEPA Record of Decision (ROD), so the Corps' NWP action will be substantially delayed beyond the standard 60-day processing time. The ESA consultation request will be reviewed by BLM and cooperating agencies prior to transmittal to the USFWS. The Native American Heritage Commission (NAHC) sacred lands file search request (a precursor to tribal coordination) was initiated on January 7, 2019 and again on February 19, 2019. The NAHC responded to the Corps on February 22, 2019. The Corps will initiate tribal coordination with all federally recognized tribes and interested parties following submittal of a complete PCN (dependency). Target date for the Corps final action/verification: April 30, 2021.         

Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The NWP action requires Section 106 NHPA consultation (BLM Lead Federal Agency) and a Section 7 ESA Biological Opinion from USFWS (Corps Lead Federal Agency). ESA and tribal coordination letters are drafted and pending transmittal, but cannot be completed until the submittal of a complete PCN (dependency). Both the 106 and ESA consultations are dependent on the NEPA Record of Decision (ROD), so the Corps' NWP action will be substantially delayed beyond the standard 60-day processing time. The ESA consultation request will be reviewed by BLM and cooperating agencies prior to transmittal to the USFWS. The Native American Heritage Commission (NAHC) sacred lands file search request (a precursor to tribal coordination) was initiated on January 7, 2019 and again on February 19, 2019. The NAHC responded to the Corps on February 22, 2019. The Corps will initiate tribal coordination with all federally recognized tribes and interested parties following submittal of a complete PCN (dependency). Target date for the Corps final action/verification: April 30, 2021.         

Project

PROJECT WEBSITE: Replacement of Lines 901 and 903

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
03/29/2021

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production

SECTOR
Conventional Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

Plains Pipeline, L.P. filed a right-of-way application with the Bureau of Land Management (BLM) Bakersfield Office on January 9, 2018, for the replacement and abandonment of existing oil pipelines 901 and 903. The project spans multiple local, State and Federal jurisdictions. The proposed project consists of installation and operation of approximately 123.4 miles of replacement pipelines 901R and 903R, supporting access roads, valves, and pump stations. 

The project was paused from November 1, 2019 to January 4, 2021. Plains Pipeline, L.P. submitted an updated project description and supporting documents during this time. A Standard Individual Permit (SIP) application was submitted to the United States Army Corps of Engineers on October 5, 2020 to replace the original Nation Wide Permit (NWP) 12 Per-Construction Notification(PCN) application while the project was in paused status.

field_status
System Comments
Final Required Milestone Date of 04/30/2021 for Final Verification/Permit Decision Rendered has passed by 5 business days
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Final Verification/Permit Decision Rendered (Agency Action)
Current Target Date:
Milestone Details

The NWP action requires Section 106 NHPA consultation (BLM Lead Federal Agency) and a Section 7 ESA Biological Opinion from USFWS (Corps Lead Federal Agency). ESA and tribal coordination letters are drafted and pending transmittal, but cannot be completed until the submittal of a complete PCN (dependency). Both the 106 and ESA consultations are dependent on the NEPA Record of Decision (ROD), so the Corps' NWP action will be substantially delayed beyond the standard 60-day processing time. The ESA consultation request will be reviewed by BLM and cooperating agencies prior to transmittal to the USFWS. The Native American Heritage Commission (NAHC) sacred lands file search request (a precursor to tribal coordination) was initiated on January 7, 2019 and again on February 19, 2019. The NAHC responded to the Corps on February 22, 2019. The Corps will initiate tribal coordination with all federally recognized tribes and interested parties following submittal of a complete PCN (dependency). Target date for the Corps final action/verification: April 30, 2021.         

Response Date