FAST-41 Missed Date: Fish and Wildlife Coordination Act Review (DOI – FWS)

Submitted by Anonymous on

Final Required Milestone Date of 10/01/2020 for Fish and Wildlife Coordination Act review concluded has passed by 5 business days

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Status:
Cancelled
POC Name:
Chuck Ardizzone
POC Title:
Field Supervisor

Description:

Due to staffing changes/limitations, FWS will not complete a separate FWCA planning document for the project. This action was cancelled.

Milestones:

Action Agency requests consultation regarding conservation of fish and wildlife resources (Agency Action)
Completed Date:
Fish and Wildlife Coordination Act review concluded (Agency Action)
Current Target Date:
Milestone
Fish and Wildlife Coordination Act review concluded (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Port of Corpus Christi's Website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
07/17/2024

7 out of 7

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Ports and Waterways

SECTOR
Ports and Waterways

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Army

LEAD AGENCY
Department of the Army, US Army Corps of Engineers - Regulatory

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

The purpose of the proposed project is to construct a channel with the capability to accomodate the transit of fully laden Very Large Crude Carriers (VLCCs) from multiple locations on Harbor Island, TX and into the Gulf of Mexico. 

field_status
System Comments
Final Required Milestone Date of 10/01/2020 for Fish and Wildlife Coordination Act review concluded has passed by 5 business days
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
Fish and Wildlife Coordination Act review concluded (Agency Action)
Current Target Date:
Response Date