FAST-41 Missed Date: Authorization and Certification

Submitted by alexandria.and… on

Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 08/07/2020 and extended to 09/30/2020

Action
Project Name: Responsible Agency:
US Army Corps of Engineers - Civil Works
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
James Ross
POC Title:
Supervisory Archaeologist, U.S. Army Corps of Engineers

Description:

Real estate license required from Corps of Engineers. Easement to follow construction.

Additional Points of Contact:

Susan Monson, Realty Specialist

Rock Island District Real Estate Section

Susan.C.Monson@usace.army.mil

 

Steve Stickle, Supervisory Realty Specialist

Rock Island District Real Estate Section

steven.w.stickle@usace.army.mil

 

Milestones:

Initial application received (Applicant Action)
Completed Date:
Completed application received (Applicant Action)
Completed Date:
Issuance of decision for permit/approval (Agency Action
Current Target Date:
Milestone
Issuance of decision for permit/approval (Agency Action
Current Target Date:
Project

PROJECT WEBSITE: Cardinal-Hickory Creek 345 kV Transmission Line Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
10/06/2023

10 out of 10

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Electricity Transmission

SECTOR
Electricity Transmission

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of Agriculture

LEAD AGENCY
Department of Agriculture, Rural Development

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Civil Works

Description:

Dairyland Power Cooperative ("Dairyland"), a cooperative organized under the
laws of Wisconsin, American Transmission Company LLC by its corporate
manager, ATC Management Inc., (together, "ATC"), and ITC Midwest LLC ("ITC
Midwest") (all collectively, "Utilities") propose to construct and own the Cardinal—
Hickory Creek Transmission Line Project ("Project"), a 345 kilovolt ("kV")
transmission line connecting northeast Iowa and south-central Wisconsin.


The U.S. Department of Agriculture's Rural Utilities Service is currently the lead
federal agency for the preparation of an Environmental Impact Statement for the
Project. The U.S. Fish and Wildlife Service and the U.S. Army Corps of
Engineers are Cooperating Agencies. The Notice of Intent was published on
October 18, 2016. The Scoping Report was released around June 23, 2017.
The RUS's consultant is currently drafting the Preliminary Draft Environmental
Impact Statement (PDEIS).

field_status
System Comments
Triggered missed date from extending Issuance of decision for permit/approval within 30 days of its current target date which was 08/07/2020 and extended to 09/30/2020
Approver Comments
The missed date functionality was erroneously triggered due to a malfunction of the Permitting Dashboard.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
Yes
New Milestone
Issuance of decision for permit/approval (Agency Action
Current Target Date:
Response Date