USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Missed Date: Endangered Species Act Consultation (DOI-FWS)

Submitted by Anonymous on

Final Required Milestone Date of 08/11/2020 for Conclusion of ESA Consultation has passed by 5 business days

Action
Project Name: Responsible Agency:
Fish and Wildlife Service
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
Paused
POC Name:
Steve Henry
POC Title:
Field Supervisor
POC Email:

Description:

The endangered Gaviota tarplant,  San Joaquin wooly threads, California jewel flower, Kem mallow, Santa Barbara County Distinct Population Segment of the California tiger salamander and its critical habitat, blunt-nosed leopard lizard, southwestern willow flycatcher and its critical habitat, least Bell's vireo and its critical habitat, California condor, tidewater goby and its critical habitat, San Joaquin kit fox, Nelson's antelope squirrel, giant kangaroo rat, Tipton kangaroo rat, and arroyo toad and its critical habitat, as well as the threatened Kem primrose sphinx moth and California red-legged frog and its critical habitat occur in the project area; therefore consultation pursuant to section 7 of the Endangered Species Act will be necessary.  FWS received a a request to initiate consultation on July 2, 2019 and on August 1, 2019 requested additonal information needed to complete consultation.

Milestones:

ESA Consultation Request Package Submitted (Agency Action)
Completed Date:
FWS determines ESA Consultation Package is Complete - Formal (Agency Action)
Current Target Date:
ESA Consultation Concludes (Agency Action)
Current Target Date:
Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: Replacement of Lines 901 and 903

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

Paused

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
PAUSED

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
SUBJECT TO CHANGE

1 out of 1

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Conventional Energy Production

SECTOR
Conventional Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Description:

The proposed Plains Pipeline will replace the existing pipelines known as Line 901 and Line 903 with the Line 901R and Line 903R pipelines. The proposed Project consists of the installation and operation of approximately 123.4 miles of replacement pipelines, supporting access roads, valves, and pump stations.

The proposed project is in the planned stage based on several factors. The applicant is preparing an application and Plan of Development for submittal to the project team. Until the application and Plan of Development is received, the proposed project may not be Initiated. In addition, a NEPA contractor is needed. The proposed project will be in the in progress stage in the First Quarter of Calendar Year 2019.

field_status
System Comments
Final Required Milestone Date of 08/11/2020 for Conclusion of ESA Consultation has passed by 5 business days
Approver Comments
The missed milestone completion date or delay was attributable to reasons beyond the control of the agency.
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
No
New Milestone
ESA Consultation Concludes (Agency Action)
Current Target Date:
Response Date