USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Milestone Extension: Right-of-Way Authorization (DOI-BLM)

Submitted by e1willia@blm.gov on

The Department of Interior is requiring a joint briefing by the Bureau of Land Management and the National Park Service on their respective authorizations for right-of-way, scheduled for June 26, 2020.  The BLM will not be able to issue its ROD until after the briefing, making June 29 the first available date for the ROD.

Prior to offering the grant of right-of-way, the BLM must first provide notice to Congress that we are about to issue a right-of-way for a large diameter pipeline.  The BLM will work to keep the intervening time as short as possible, but a reasonable estimate is within two weeks.  Thus the target date for the grant of right-of-way offer letter is July 13, 2020.

The BLM has informed the proponent of the delay in the ROD and subsequent delay in the grant of right-of-way and they have not raised any concerns.

The agency CERPO has been informed of the delay, it occurred during a coordination call today.  The delay in the BLM right-of-way will not impact other agencies' issuance of their respective authorizations.

Action
Project Name: Responsible Agency:
Bureau of Land Management
Agency Status: Cooperating under FAST-41
Cooperating under NEPA
Status:
In Progress
POC Name:
Earle Williams
POC Title:
Natural Gas Pipelines Project Manager
POC Email:

Description:

BLM is responding to an application for a right-of-way on public lands. If the BLM offers a right-of-way grant to the applicant, the target date for this action will be the offer date of the right-of-way grant to the applicant for their signature. 

The Alaska Gasline Development Corporation (Applicant) plans to construct one integrated liquefied natural gas (LNG) Project (Project) with interdependent facilities for the purpose of liquefying supplies of natural gas from Alaska, in particular from the Point Thomson Unit (PTU) and Prudhoe Bay Unit (PBU) production fields on the Alaska North Slope (North Slope), for export in foreign commerce and for in‐state deliveries of natural gas.  

The new Liquefaction Facility would be constructed on the eastern shore of Cook Inlet just south of the existing Agrium fertilizer plant on the Kenai Peninsula, approximately 3 miles southwest of Nikiski and 8.5 miles north of Kenai.  The Liquefaction Facility would include the structures, equipment, underlying access rights, and all other associated systems for final processing and liquefaction of natural gas, as well as storage and loading of LNG, including terminal facilities and auxiliary marine vessels used to support Marine Terminal operations (excluding LNG carriers [LNGCs]).  The Liquefaction Facility would include three liquefaction trains combining to process up to approximately 20 million metric tons per annum (MMTPA) of LNG.  Two 240,000‐cubic‐meter tanks would be constructed to store the LNG.  The Liquefaction Facility would be capable of accommodating two LNGCs.  The size of LNGCs that the Liquefaction Facility would accommodate would range between 125,000–216,000‐cubic‐meter vessels.  In addition to the Liquefaction Facility, the LNG Terminal would include the following interdependent facilities:  Mainline: A new 42‐inch‐diameter natural gas pipeline approximately 807 miles in length would extend from the Liquefaction Facility to the GTP in the PBU, including the structures, equipment, and all other associated systems.  

The proposed design anticipates up to eight compressor stations; one standalone heater station, one heater station collocated with a compressor station, and six cooling stations associated with six of the compressor stations; four meter stations; 30 Mainline block valves (MLBVs); one pig launcher facility at the GTP meter station, one pig receiver facility at the Nikiski meter station, and combined pig launcher and receiver facilities at each of the compressor stations; and associated infrastructure facilities.  Associated infrastructure facilities would include additional temporary workspace (ATWS), access roads, helipads, construction camps, pipe storage areas, material extraction sites, and material disposal sites.  Along the Mainline route, there would be at least five gas interconnection points to allow for future in‐state deliveries of natural gas.  The approximate locations of three of the gas interconnection points have been tentatively identified as follows:  milepost (MP) 441 to serve Fairbanks, MP 763 to serve the Matanuska‐Susitna Valley and Anchorage, and MP 807 to serve the Kenai Peninsula.  The size and location of the other interconnection points are unknown at this time.  

Milestones:

Initial application received (Agency Action)
Completed Date:
Completed application received (Agency Action)
Completed Date:
Final decision/agency action (Agency Action)
Current Target Date:
Milestone Details

The milestone target date for a BLM record of decision for NEPA is June 24, 2020, one week after the target date for the Endangered Species Act consultation.

The Grant of Right-Of-Way cannot be authorized until Section 106 consultation is complete and the NHPA complied with.  In addition, upon completion of the NEPA process the BLM must notify Congress that we are preparing to issue a right-of-way for a large diameter pipeline.  The milestone target date for the right-of-way offer letter is July 2, 2020.

There are no milestones to display.

There are no milestones to display.

Milestone
Final decision/agency action (Agency Action)
Current Target Date:
Milestone Details

The milestone target date for a BLM record of decision for NEPA is June 24, 2020, one week after the target date for the Endangered Species Act consultation.

The Grant of Right-Of-Way cannot be authorized until Section 106 consultation is complete and the NHPA complied with.  In addition, upon completion of the NEPA process the BLM must notify Congress that we are preparing to issue a right-of-way for a large diameter pipeline.  The milestone target date for the right-of-way offer letter is July 2, 2020.

Project

PROJECT WEBSITE: http://alaska-lng.com/

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
12/10/2025

20 out of 20

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Pipelines

SECTOR
Pipelines

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Federal Energy Regulatory Commission

LEAD AGENCY
Federal Energy Regulatory Commission

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of Commerce

Department of Commerce, National Oceanic and Atmospheric Administration

Department of Homeland Security

Department of Homeland Security, US Coast Guard

Department of the Interior

Department of the Interior, Bureau of Land Management

Department of the Interior

Department of the Interior, Fish and Wildlife Service

Department of the Army

Department of the Army, US Army Corps of Engineers - Regulatory

Department of Energy

Department of Energy, Office of Fossil Energy

Department of the Interior

Department of the Interior, National Park Service

Department of Energy

Department of Energy

Description:

The Alaska LNG Project is comprised of the following integrated and interdependent facilities:  a liquefied natural gas (LNG) terminal in Southcentral Alaska designed to produce up to 20 million metric tons per annum of LNG; an approximately 807-mile, 42-inch diameter gas pipeline; a gas treatment plant (GTP) within the Prudhoe Bay Unit (PBU) on the North Slope; an approximately 1-mile, 60-inch diameter gas transmission line connecting the GTP to the PBU gas production facility; and an approximately 63 mile, 32-inch diameter gas transmission line connecting the GTP to the Point Thomson gas production facility.  The mainline of the Alaska LNG Project will traverse over 800 miles from the GTP on the North Slope of Alaska through several boroughs before it crosses Cook Inlet and connects with the liquefaction plant and marine terminal in Nikiski, Alaska. 

Fast-41 Initiation Notice

Project Application and Supporting Documents

Federal Agency Actions

FERC Litigation

  • None filed.

 

For improved transparency, FERC is providing this supplemental table to reflect the additional federal authorizations that may be required for the Alaska LNG Project.  

Additional Federal Agency Permitting Timetable for the Alaska LNG Project 
Responsible Agency Federal Permit/Review Status Applicable Timelines
US Coast Guard Letter of Recommendation Complete Receipt of Letter of Intent:  May 15, 2014
Receipt of Waterway Suitability Assessment:  March 18, 2016
Letter of Recommendation to FERC:  August 17, 2016

 

Last updated May 22, 2020

field_status
System Comments
Furthest out
Original Target Date: 06/04/2020
Milestone: Issuance of decision for permit/approval

Requested extensions greater than 30 days for this Action are shown below:

Issuance of decision for permit/approval extended by 39
From: 07/02/2020
To: 07/13/2020
Missed Date Process
No
Missed Date Triggered by Extension
No