FAST-41 Missed Date: Section 106 Review

Submitted by fmarcell@blm.gov on

Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 02/21/2020 and extended to 06/15/2020

Action
Project Name: Responsible Agency:
Bureau of Land Management
Status:
In Progress
POC Name:
Jim Stobaugh
POC Title:
Project Manager
POC Email:
SHPO:

New Mexico

Milestones:

Consultation initiated with SHPO/THPO (Agency Action)
Completed Date:
Section 106 consultation concluded (Agency Action)
Current Target Date:
Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Project

PROJECT WEBSITE: ePlanning BLM NM website

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
08/14/2020

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Renewable Energy Production

SECTOR
Renewable Energy Production

Project Category

CATEGORY
Project Category FAST-41 Covered Projects
Major Infrastructure Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Land Management

Description:

The purpose of the Borderlands Wind Project is to construct, operate and maintain the energy-generating infrastructure in Catron County, New Mexico sufficient to provide up to 100 megawatts (MW) of renewable wind energy to the electrical transmission grid in the Southwest.

field_status
System Comments
Triggered missed date from extending Section 106 consultation concluded within 30 days of its current target date which was 02/21/2020 and extended to 06/15/2020
Previous Action Status
New Action Status
Missed Date Process
No
Missed Date Triggered by Extension
Yes
New Milestone
Section 106 consultation concluded (Agency Action)
Current Target Date:
Response Date