Milestone Extension: Supplemental Environmental Assessment (EA)

Submitted by giannina.dimai… on

This extension would allow the proponent time to submit required documentation (survey plats and Joint Use Agreement/Permits for ROW). A detailed survey plat and legal description of where the proposed right of way will be within the existing easements are necessary, to ensure accuracy and to show that all the requirements of the legal description have been met. Documents are required to proceed in meeting the target dates. 

Action
Project Name: Responsible Agency:
Bureau of Indian Affairs
Status:
In Progress
POC Name:
Lenora Bates
POC Title:
Realty Specialist

Milestones:

Determination to Prepare a Supplemental EA
Completed Date:
Issuance of a Draft Supplemental EA
Current Target Date:
Issuance of a Final Supplemental EA (Agency Action)
Current Target Date:
EA Process Concluded
Current Target Date:
Milestone
EA Process Concluded
Current Target Date:
Project

All dates below are specific to the schedule of the Environmental Review and Permitting processes for this project.

In Progress

ENVIRONMENTAL REVIEW AND PERMITTING STATUS
IN PROGRESS

icon_calendar

ESTIMATED COMPLETION DATE OF ENVIRONMENTAL REVIEW AND PERMITTING
04/30/2026

4 out of 4

ENVIRONMENTAL REVIEW AND PERMITTING PROCESSES
COMPLETED

Broadband

SECTOR
Broadband

Project Category

CATEGORY
Project Category FAST-41 Covered Projects

Department of the Interior

LEAD AGENCY
Department of the Interior, Bureau of Indian Affairs

View FAST-41 Postings by Agencies

Other Agencies with Actions or Authorizations:

Department of the Interior

Department of the Interior, Bureau of Land Management

Description:

The Gallup McKinley County School proposes to deploy a reliable, affordable, scalable, and future-proofed broadband network that bridges the digital divide for the foreseeable future in one of the most remote, isolated, high-cost, and difficult to serve areas of the United States. The Gallup McKinley County Schools E-Rate Funded Broadband Project consists of constructing approximately 65 miles of middle mile fiber optic network on the Navajo Nation to connect the school district with high-speed Internet connectivity to speeds of 1 Gbps or greater.

field_status
System Comments
Furthest out
Original Target Date: 12/23/2025
Milestone: EA Process Concluded

Requested extensions greater than 30 days for this Action are shown below:

EA Process Concluded extended by 128
From: 12/23/2025
To: 04/30/2026
Missed Date Process
No
Missed Date Triggered by Extension
No
Original Milestone
EA Process Concluded
Current Target Date:
Furthest Original Target Date Milestone
EA Process Concluded
Current Target Date: