Permitting Action Modification History

Complete
Agency completed the environmental assessment, issuing FONSI ahead of scheduled due date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to Prepare a Supplemental EA 01-31-2025 01-27-2025 --- Yes
Issuance of a Final Supplemental EA (Agency Action) 11-24-2025 03-13-2026 --- Yes
EA Process Concluded 12-23-2025 03-30-2026 --- Yes
In Progress
Final EA issued 3/13/2026, ahead of target date (3/25).  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to Prepare a Supplemental EA 01-31-2025 01-27-2025 --- Yes
Issuance of a Final Supplemental EA (Agency Action) 11-24-2025 03-13-2026 --- Yes
EA Process Concluded 12-23-2025 04-30-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to Prepare a Supplemental EA 01-31-2025 01-27-2025 --- Yes
Issuance of a Final Supplemental EA (Agency Action) 11-24-2025 03-25-2026 --- No
EA Process Concluded 12-23-2025 04-30-2026 --- No
In Progress
This extension would allow the proponent time to submit required documentation (survey plats and Joint Use Agreement/Permits for ROW). A detailed survey plat and legal description of where the proposed right of way will be within the existing easements are necessary, to ensure accuracy and to show that all the requirements of the legal description have been met. Documents are required to proceed in meeting the target dates.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to Prepare a Supplemental EA 01-31-2025 01-27-2025 --- Yes
Issuance of a Draft Supplemental EA 10-20-2025 12-30-2025 --- No
Issuance of a Final Supplemental EA (Agency Action) 11-24-2025 03-25-2026 --- No
EA Process Concluded 12-23-2025 04-30-2026 --- No
In Progress
Determination made in advance of due date. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to Prepare a Supplemental EA 01-31-2025 01-27-2025 --- Yes
Issuance of a Draft Supplemental EA 10-20-2025 10-20-2025 --- No
Issuance of a Final Supplemental EA (Agency Action) 11-24-2025 11-24-2025 --- No
EA Process Concluded 12-23-2025 12-23-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to Prepare a Supplemental EA 01-31-2025 01-31-2025 --- No
Issuance of a Draft Supplemental EA 10-20-2025 10-20-2025 --- No
Issuance of a Final Supplemental EA (Agency Action) 11-24-2025 11-24-2025 --- No
EA Process Concluded 12-23-2025 12-23-2025 --- No